City of Lawrence
Neighborhood Resources Department
MEMORANDUM
TO: David L. Corliss, Interim City Manager
THRU: Margene Swarts, Community Development Manager
FROM: Tony L. Hoch, Projects Specialist
DATE: September 26, 2006
STAFF PRESENT FOR BID OPENING on September 19th, 2006: Tony L. Hoch, Larry E. Hamm, Alan Landis, Frank Reeb.
COMPREHENSIVE HOUSING REHABILITATION SCOPE OF WORK:
1624 E 18th St. Terr: Minor exterior painting, replace concrete driveway and sidewalk, consolidate electrical supply with 200 amp service, new and rewire lighting fixtures, bath and kitchen GFCI’s, bathroom caulking repair, plumbing access panel and steps and landing for garage entrance.
CONTRACTOR |
1624 E 18th St Terr |
Edmondson Construction |
$13,737.00 |
T & J Holdings, Inc. |
$8,464.00 |
Staff Estimate |
$9,827.00 |
Recommendation Action:
Staff recommends award of bid as follows:
1624 E 18th St Terr - T & J Holdings, Inc.
cc: Bobbie Walthall
Frank Reeb
Alan Landis