City of Lawrence
Project No. 22-CP7-606(C)
City Bid No. B06042
New Hampshire Street, Street Improvements between 6th Street and 9th Street
Mill, Overlay, Pavement Marking, Intersection Reconstruction, Mid-Block Pedestrian Crossings
BID TAB
Engineer's Estimate: $274,311.50
Bid Date:  August 29, 2006
R. D. Johnson Excavating LRM Industries Kansas Heavy Construction Linaweaver Const., Inc.
ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
  SECTION 1 - MILL, OVERLAY, PAVEMENT MARKING, CURB AND GUTTER                
1 Milling (2") S.Y. 7,913  $            2.00  $    15,826.00  $           1.70  $       13,452.10  $           2.10  $    16,617.30  $           2.25  $    17,804.25
2 Asphaltic Concrete Overlay (2") BM-2 TON 914  $          51.00  $    46,614.00  $         47.80  $       43,689.20  $         51.00  $    46,614.00  $         57.00  $    52,098.00
3 Crackfilling **** L.F. 6,000  $            0.60  $      3,600.00  $           0.55  $         3,300.00  $           0.60  $      3,600.00  $           1.00  $      6,000.00
4 Pavement Crack/Joint Membrane **** L.F. 6,000  $            1.55  $      9,300.00  $           1.50  $         9,000.00  $           1.55  $      9,300.00  $           2.00  $    12,000.00
5 Concrete Pavement Patch (Full Depth)**** S.Y. 200  $          70.00  $    14,000.00  $         83.00  $       16,600.00  $       120.00  $    24,000.00  $       100.00  $    20,000.00
6 Remove and Replace Existing Concrete Curb and Gutter L.F. 882  $          24.95  $    22,005.90  $         28.00  $       24,696.00  $         37.00  $    32,634.00  $         25.00  $    22,050.00
7 Remove Existing Brick Crosswalk and Replace With Imprinted Concrete Crosswalk EACH 1  $     6,200.00  $      6,200.00  $    7,600.00  $         7,600.00  $  17,600.00  $    17,600.00  $  24,000.00  $    24,000.00
8 Manhole Adjustment EACH 5  $        700.00  $      3,500.00  $       660.00  $         3,300.00  $       700.00  $      3,500.00  $    1,200.00  $      6,000.00
9 Valve Adjustment EACH 11  $        250.00  $      2,750.00  $       220.00  $         2,420.00  $       345.00  $      3,795.00  $       500.00  $      5,500.00
10 Cold Plastic Reflectorized Pavement Marking                    
  a)  6" Broken White Lane Line (Class A) L.F. 360  $            4.20  $      1,512.00  $           4.15  $         1,494.00  $           4.00  $      1,440.00  $           5.00  $      1,800.00
  b)  6" Dotted White Lane Line (Class A) L.F. 44  $            4.20  $         184.80  $           4.15  $            182.60  $           4.00  $         176.00  $           5.00  $         220.00
  c)  6" Solid White Lane Line (Class A) L.F. 462  $            4.20  $      1,940.40  $           4.15  $         1,917.30  $           4.00  $      1,848.00  $           5.00  $      2,310.00
  d)  12" Solid White Diagonal Line L.F. 94  $            8.40  $         789.60  $           8.30  $            780.20  $           8.00  $         752.00  $         10.00  $         940.00
  e)  24" Solid White Stop Line (Class A) L.F. 162  $          14.70  $      2,381.40  $         14.50  $         2,349.00  $         14.00  $      2,268.00  $         16.00  $      2,592.00
  f)  36" Solid White Crosswalk Line (Class A) L.F. 222  $          18.90  $      4,195.80  $         18.65  $         4,140.30  $         18.00  $      3,996.00  $         20.00  $      4,440.00
  g)  4" Broken Yellow Lane Line (Class B) L.F. 540  $            2.63  $      1,420.20  $           2.60  $         1,404.00  $           2.50  $      1,350.00  $           4.00  $      2,160.00
  h)  4" Solid Yellow Lane Line (Class B) L.F. 2,010  $            2.63  $      5,286.30  $           2.60  $         5,226.00  $           2.50  $      5,025.00  $           4.00  $      8,040.00
  i)  4" Solid Double Yellow Lane Line (Class B) L.F. 218  $            5.25  $      1,144.50  $           5.20  $         1,133.60  $           5.00  $      1,090.00  $           6.00  $      1,308.00
11 Traffic Control L.S. 1  $     4,800.00  $      4,800.00  $  10,000.00  $       10,000.00  $    3,000.00  $      3,000.00  $    4,500.00  $      4,500.00
12 Seed, Fertilize, & Mulch L.S. 1  $     1,500.00  $      1,500.00  $    1,500.00  $         1,500.00  $       650.00  $         650.00  $    3,500.00  $      3,500.00
  Total Section 1        $  148,950.90    $     154,184.30    $  179,255.30    $  197,262.25
                       
  SECTION 2 - 7TH & NEW HAMPSHIRE INTERSECTION RECONSTRUCTION                
1 Demolition * L.S. 1  $     6,265.00  $      6,265.00  $  11,000.00  $       11,000.00  $  20,800.00  $    20,800.00  $  30,000.00  $    30,000.00
2 10" Fiber Reinforced Concrete S.Y. 485  $          65.00  $    31,525.00  $         80.50  $       39,042.50  $         79.00  $    38,315.00  $       110.00  $    53,350.00
3 24" Concrete Curb and Gutter L.F. 375  $          20.95  $      7,856.25  $         15.00  $         5,625.00  $         37.00  $    13,875.00  $         20.00  $      7,500.00
4 Access Ramp ** EACH 8  $     1,000.00  $      8,000.00  $       950.00  $         7,600.00  $    1,250.00  $    10,000.00  $    2,500.00  $    20,000.00
5 Water Valve Adjustment EACH 5  $        250.00  $      1,250.00  $       220.00  $         1,100.00  $       345.00  $      1,725.00  $       500.00  $      2,500.00
6 Traffic Control L.S. 1  $   28,350.00  $    28,350.00  $  26,000.00  $       26,000.00  $  27,500.00  $    27,500.00  $  35,000.00  $    35,000.00
7 Seed, Fertilize and Mulch L.S. 1  $        900.00  $         900.00  $    1,500.00  $         1,500.00  $       650.00  $         650.00  $    3,500.00  $      3,500.00
  Total Section 2        $    84,146.25    $       91,867.50    $  112,865.00    $  151,850.00
                       
  SECTION 3 - MID-BLOCK PEDESTRIAN CROSSINGS                
1 Demolition * L.S. 1  $     1,800.00  $      1,800.00  $    5,000.00  $         5,000.00  $    6,000.00  $      6,000.00  $  25,000.00  $    25,000.00
2 8" Fiber Reinforced Concrete *** C.Y. 33  $        220.00  $      7,260.00  $       320.00  $       10,560.00  $       310.00  $    10,230.00  $       300.00  $      9,900.00
3 "Brick Pattern" Imprinted Concrete Surface S.Y. 40  $        100.00  $      4,000.00  $         67.50  $         2,700.00  $       145.00  $      5,800.00  $       220.00  $      8,800.00
4 Access Ramp ** EA 4  $     1,200.00  $      4,800.00  $       950.00  $         3,800.00  $    1,250.00  $      5,000.00  $    2,500.00  $    10,000.00
5 24" Concrete Curb and Gutter L.F. 191  $          20.95  $      4,001.45  $         15.00  $         2,865.00  $         37.00  $      7,067.00  $         20.00  $      3,820.00
6 Heat Fused Preformed Thermoplastic Marking Material                  
  a)  24" Solid White Stop Line L.F. 51  $          14.70  $         749.70  $         14.50  $            739.50  $         14.00  $         714.00  $         16.00  $         816.00
  b)  36" Solid White Crosswalk Line L.F. 144  $          18.90  $      2,721.60  $         18.65  $         2,685.60  $         18.00  $      2,592.00  $         20.00  $      2,880.00
7 1" PVC Pipe, 18" Deep (4 @ 65' each) L.F. 260  $          10.00  $      2,600.00  $         10.00  $         2,600.00  $         10.00  $      2,600.00  $         12.00  $      3,120.00
8 12" x 12" x 12" Quazite Open Bottom With Lid Marked 'Street Lighting' EA 4  $        350.00  $      1,400.00  $       350.00  $         1,400.00  $       350.00  $      1,400.00  $       500.00  $      2,000.00
9 Traffic Control L.S. 1  $     4,000.00  $      4,000.00  $    1,600.00  $         1,600.00  $    3,500.00  $      3,500.00  $    4,500.00  $      4,500.00
10 Seed, Fertilize & Mulch L.S. 1  $        800.00  $         800.00  $    1,500.00  $         1,500.00  $       300.00  $         300.00  $    1,800.00  $      1,800.00
  Total Section 3        $    34,132.75    $       35,450.10    $    45,203.00    $    72,636.00
                       
  GRAND TOTAL OF SECTIONS 1,2, & 3    $  267,229.90    $     281,501.90    $  337,323.30    $  421,748.25