Memorandum

City of Lawrence

Department of Public Works

 

TO:

Dave Corliss, Debbie Van Saun

FROM:

Chuck Soules

CC:

Terese Gorman, David Woosley

Date:

August 23, 2006

RE:

Project No. 36-CP12-704(S)

Kasold Drive, Peterson Road to the KTA Bridge

Street. Storm Sewer Improvements

August 29, 2006 Agenda Item

 

Please include the following item on the City Commission consent agenda for consideration at the August 29, 2006 meeting:

Project Description.  This project will include the reconstruction of Kasold Drive from Peterson Road north to the KTA.  The improvements will include a wide single-lane street in each direction (similar to Princeton Boulevard and Lawrence Avenue), with curb and gutter, landscaped median, roundabouts at Grand Vista Drive and Tillerman Drive, recreation path and sidewalk, and waterline.

Project History.  The project was placed on the City’s 5-Year Plan with KDOT in April 2004 and has been in the City’s CIP since 1999.

November 18, 2004

Neighborhood Meeting

December 12, 2005

Open House

January 11, 2005

Present to City Commission

January 18, 2005

Presented Revised Alternatives

 

Project Status.  This project is scheduled to bid in October 2006.  Final plans are approved through KDOT.   

 

Project Funding. 

 

 

TOTAL

KDOT

CITY

Construction Estimate

$4,352,000

$3,481,000

$871,000

Construction Engineering

130,000

104,000

26,000

Engineering

250,000

-0-

250,000

Right-of-Way

50,000

-0-

50,000

 

$4,780,000

$3,585,000

$1,197,000

 

In September 2004, Resolution 6566 authorized the issuance of Bonds in the amount of $770,000 for this project.

 

 

 

 

 

Action Request.  Adopt Resolution No. 6676 authorizing the Mayor to execute the City/State Agreement No. 139-06 with the Kansas Department of Transportation, and authorize the Mayor to execute Agreement No. 126-06.

 

Adopt Resolution No. 6678 authorizing the issuance of bonds in the amount of $1,200,000.

Please let me know if there are any questions.

 

Respectfully submitted,

Charles F. Soules, P.E.

Director of Public Works

 

CFS/je

 