Memorandum

City of Lawrence

Public Works

 

TO:

Dave Corliss, Debbie Van Saun, Terese Gorman, Steve Lashley

FROM:

Chuck Soules

Date:

August 16, 2006

RE:

Asphalt Pricing Adjustment

August 22, 2006 Agenda Item

 

The cost of construction has significantly increased during the 2006 construction season because of increased asphalt pricing: 

2004

$33 / Ton of asphalt

2005

$35 / Ton of asphalt

2006

$44 / Ton of asphalt

 

The extreme volatility of asphalt oil has made it difficult for contractors to provide competitive pricing.  In June KDOT adopted a specification for the price adjustment of asphalt materials.  This specification is very specific, using current market conditions and specific percentage of asphalt and oil used in the various mix designs used by KDOT.  The attached specification simplifies a price adjustment for asphalt oil increases/decreases, but is based on the same principals used by KDOT.  This policy has been reviewed by our local contractors.

 

KDOT’s website provides the following oil prices:

June

$350 / Short Ton

July

$354 / Short Ton

August

$375 / Short Ton

 

KDOT did not provide a price adjustment in June/July; however, in August a $20 increase over July pricing would incur a $1.00/Ton adjustment in city projects.

 

This year the city Mill and Overlay Projects included:

Phase 1

10,500 Tons

Phase II

  5,500 Tons

Phase III

  6,000 Tons

 

The adjustment will be made monthly with the base price being established in the month the bid was received.  This will provide better competitive bids for the city and provide a comfort level for the contractor to provide competitive pricing.

 

Please let me know if you have any questions.

 

ACTION REQUESTED:  Approve specification for the price adjustment of asphalt materials.

 

Respectfully submitted,

Charles F. Soules, P.E.

Director of Public Works

 

Attachment:  Specification