ITEM NO. 12A:         RS-2 [RS7] TO PRD-1; .85 ACRES; 1511 HASKELL AVENUE (SLD)

 

Z-06-15-06:  A request to rezone a tract of land approximately .85 acres, from RS-2 [RS7] (Single-Family Residence) to PRD-1 (Planned Residential). The property is located at 1511 Haskell Avenue. Submitted by Landplan Engineering for Jerry Willis, property owner of record.

 

ITEM NO. 12B:         PRELIMINARY DEVELOPMENT PLAN FOR HANSCOM-TAPPAN ADDITION III; .85 ACRES; 1511 HASKELL AVENUE (SLD)

 

PDP-06-05-06:  Preliminary Development Plan for Hanscom-Tappan Addition III. Approximately .85 acres. The property is located at 1511 Haskell Avenue. Submitted by Landplan Engineering for Jerry Willis, property owner of record.

 

Items 12A & 12B were discussed simultaneously.

 

STAFF PRESENTATION

Ms. Day, Planning Staff, gave an introduction of the request to rezone 1511 Haskell Avenue.  The surrounding area includes previous phases of a planned unit development.  There is a request for reduction in peripheral setback.   The side setbacks are consistent with the remainder of the development plan.  This is the third waiver on the project; the applicant has reached an agreement.  In regard to the reduction to the peripheral setback, the original phase respects the original setback and Exhibit A shows the area becoming a common open space with the north side at Anna Tappen Way.  

 

APPLICANT PRESENTATION

CL Maurer, Landplan, for applicant appeared to answer any questions posed by the Planning Commission. 

 

Jennings asked if the applicant the builder of the existing houses in the development.

 

Maurer replied that the applicant is the builder and there is not yet a homeowners association. 

 

PUBLIC HEARING

No member of the public spoke regarding this item.

 

COMMISSION DISCUSSION

Harris questioned the connection of the peripheral setback reduction and the variance for the setback. 

 

Burress asked if it made a difference whether the PDP states a waiver or variance is requested. 

 

Day stated it does not matter. 

 

Erickson pointed out that concrete is misspelled on the plan.

 

ACTION TAKEN

ITEM NO. 12A:

Moved by Jennings, seconded by Harris, to recommends approval of the .85 acres from RS-2 [RS7] (Single-Family Residence) District to PRD-1 (Planned Residential District) and forwarding it to the City Commission with a recommendation for approval based on the findings of fact found in the body of the staff report and subject to the following conditions:

1.      Recording of a final plat prior to publication of the rezoning ordinance;

2.      Approval of a preliminary development plan prior to the publication of a rezoning ordinance.

3.      Provision of a note that indicates housing type shall be limited to single-family detached dwelling units.

 

 

Motion passed unanimously, 8-0.

 

 

ITEM NO. 12B:

Moved by Jennings and seconded by Harris to recommend approval of the Preliminary Development Plan for Hanscom-Tappan III PRD and forwarding it to the City Commission with a recommendation for approval with 2 waivers and subject to the following conditions:

 

1.      Provision of a revised Preliminary Development Plan to include the following changes as noted by City Staff:

a.      Revision to General notes Number 6 to be removed as not applicable to this development.

b.      Provision of a revised Preliminary Development Plan to restrict occupancy of the homes to comply with the definition of family applicable to conventional single-family (RS) districts.

c.      Provision of a revised Preliminary Development Plan to list all waivers associated with the proposed development.

d.      Provision of a note that states “Conformance with the general architectural character of the surrounding area shall be required and building elevations shall be provided with the submission of the Final Development Plan for approval.”

2.      Execution of an agreement not to protest the formation of a benefit district for future intersection improvements for 15th Street and Haskell Avenue.

 

 

 

 

 

 

Waivers (PUD’s): The proposed development includes following requests to reduce required setbacks as follows:

 

1.            Reduction of the required side yard from 10’ to 5’ for Phase III of the development, thus being applicable to the entire PRD.

2.            Reduction of the peripheral setback from 35’ to 20’ for Lot 1, Block 1 proposed Hanscom-Tappan III adjacent to Haskell Avenue.

3.             Reduction of required open space to 0.

 

Motion passed unanimously, 8-0.