Memorandum
City of
City Manager’s Office
To: |
Dave Corliss Interim City
Manager |
From: |
|
cc: |
Chuck Soules,
Public Works Director Aviation Advisory
Board |
Date: |
August 10, 2006 |
Re: |
Agenda item |
Please place the following item on the City Commission consent agenda for consideration at their August 15, 2006 meeting:
Project Status. Construction bids were opened on May 16th for
Schedules I and II for the parallel taxiway construction project. The bid from Hamm In. came in at an amount
higher than the funding available from FAA.
City staff worked with
A grant application was submitted to FAA on June 22, 2006 requesting FAA
participation for the project. Today we
received a grant offer from FAA for 95% of the project, with a maximum
financial obligation of $1,398,945.
Commission Action. Staff recommends acceptance of the FAA grant offer. Therefore, we seek City Commission approval to authorize the Interim City Manager to execute the grant agreement for the amount noted above.