Memorandum
City
of
Utilities
Department
TO: |
David Corliss |
FROM: |
|
CC: |
|
Date: |
|
RE: |
|
Please include the following information on the consent agenda
for the City Commission meeting of
Phase II - Downtown
Waterline Improvements – Change Order:
Project History:
The current project includes waterline improvements along
A date was set
by the City Commission for Phase II of the waterline improvements for
The City
Commission awarded the project in the amount of $1,599,584.74 to Nowak
Construction on
The City
Commission approved an incentive program on June 6, 2006 to charge property
owners the material cost for fire line improvements in the 700 and 800 blocks and allow City
crews to complete the installation at no cost to the property owner. The agreement
would require the property owner to install fire sprinkler systems inside the
building within a 5 year period.
Project Status :
As of July 26, 2006, the contractor has 26 working days for the
waterline activities and 12 working days for the Phase III (
Mill and Overlay / Cleanup).
Waterline work along the east side of
Details:
The fire
line incentive program was approved by the CC on June 6, 2006 and staff noted
in the discussions and memo that various logistical arrangements would require
contact with property owners on a case by case basis. The first step was to
contact property owners, answer questions and determine their level of interest. Upon completion, staff would have a better
understanding to develop a realistic timeframe in pursuing a fire line installation
for their property and the associated coordination with the waterline work.
Over
the past two months, Staff has contacted the business owners in the 700 and 800
block of
At
this time, it is reasonable to anticipate that the timing of the mill and
overlay in the current contract will conflict with the installation of new fire
lines. Completing the mill and overlay (
The original contract included 70 working days for the waterline
installation ( Phase I – East side & Phase II –
west side) and 12 working days for Phase
III Construction activities. Phase III included the mill and overlay, final cleanup
and punch list activities. Removing the Mill and Overlay from the project
will allow full traffic and pedestrian
access along
Project Funding:
Funding for this project is from
the non-bonded construction fund for 2006 waterline improvements.
Action Request:
Utilities staff requests the City Commission to approve the following
change order for the Downtown Waterline Contract with Nowak Construction
Company:
Thank you for your assistance.
Please advise if you have any questions.