Memorandum
City of
Public Works
TO: |
Dave Corliss |
FROM: |
Chuck Soules |
CC: |
Debbie Van Saun, Terese Gorman |
Date: |
July 31, 2006 |
RE: |
August 8, 2006
Agenda Item Alley Reconstruction, Project No. 18-CP5-506(C) |
The alley in the 1000 block
between
The City Engineer prepared plans to replace/reconstruct the alley. In a meeting with adjacent business owners on Monday, July 24, 2006, the consensus was that the businesses did not want the City to complete this project. Attached is a list of the business owners in attendance.
The problem is timing. Although the businesses feel the alley needs to be rebuilt, there are several events scheduled and the alley will be needed for deliveries. The best time to schedule this work would be the end of May to the first of August. This alley reconstruction will not be able to proceed during the summer of 2007 because the water main project is scheduled to be working in this block.
At this time it is not recommended to proceed with this project. We will look to complete this project possibly in 2008.
Please let me know if there are any questions.
Respectfully submitted,
Charles F. Soules, P.E.
Director of Public Works
CFS/je