PROJECT NAME

  AMOUNT

FINANCED

OTHER

TOTAL
RECEIPTS

 EXPENDITURES

ENCUMBRANCES

 AVAILABLE
BALANCE

General Contractor

Status

W. 6th St., Wakarusa to SLT

      400,000

 

0.00

0.00

                         -  

534,942.25

     (534,942.25)

HAMM / KDOT

Complete

W. 6th St., Wakarusa to SLT

   3,295,000

5,508,915.28

209,927.44

5,718,842.72

       5,718,554.74

0.00

             287.98

HAMM

 

 Kasold Bridge Improvement

 

                    -  

  1,321,000.00

   1,321,000.00

       1,321,000.00

                          -  

                     -  

King Const.,

Heston, KS.

 

KU Fire Station, 23rd & Iowa, STA 5

   5,000,000

4,848,589.00

1,360.00

4,849,949.00

       5,039,384.36

262,930.26

     (452,365.62)

First Management

 

Monterey Way, Stetson Dr

   4,850,000

2,749,966.40

0.00

2,749,966.40

       2,033,826.93

72,187.81

      643,951.66

King’s Const.

 

2004 Fire Truck Purchase

 

301,200.00

0.00

301,200.00

          278,683.19

20,893.00

          1,623.81

N/A

 

2005 Fire Truck Purchase

 

0.00

0.00

0.00

          695,271.00

0.00

     (695,271.00)

N/A

 

23rd & Harper Geometric Imps

      400,000

0.00

0.00

0.00

            22,466.79

6,443.06

       (28,909.85)

BG Consultants

Bids Jan. 08

2006 Overlay, Phase II

      700,000

0.00

0.00

0.00

          189,914.19

510,085.81

     (700,000.00)

R. D. Johnson

 

Airport Runway Reconstruction

 

0.00

1,536,501.00

1,536,501.00

       1,498,960.45

126,230.99

       (88,690.44)

HAMM

Project yet to be funded by FAA

Kasold, 15th to Clinton Parkway

   6,750,000

250,875.00

0.00

250,875.00

          614,176.72

4,487,632.09

  (4,850,933.81)

R. D. Johnson

Under construction

Hanscom Tappan, 2nd Plat

      350,000

0.00

13,458.26

13,458.26

          129,676.06

0.00

     (116,217.80)

R. D. Johnson

Complete

3rd St, Alabama to Illinois

      140,000

140,490.00

0.00

140,490.00

            83,313.02

1,170.00

        56,006.98

LRM Industries

Complete

2002 Traffic Signals

      200,000

203,545.04

0.00

203,545.04

          209,685.77

0.00

         (6,140.73)

City Staff

 

N. 2nd & Locust Geometric

      240,000

0.00

0.00

0.00

            63,709.44

168,112.56

     (231,822.00)

TranSystems Engineering

Bids Oct. 07

Lake Pointe, Clinton Parkway to 22nd

   1,166,250

752,625.00

147,663.97

900,288.97

          929,197.26

0.00

       (28,908.29)

LRM Industries

Complete

Monterey Way, Peter to GV

   2,620,000

2,628,167.00

0.00

2,628,167.00

       1,321,170.02

100,027.61

   1,206,969.37

King’s Const.

 

23rd St Access Management

      550,000

150,525.00

0.00

150,525.00

          108,235.43

42,837.71

            (548.14)

HNTB Engineering

Bids Jan. 07

Peterson, Kasold to Monterey Way

   3,420,000

3,423,942.00

0.00

3,423,942.00

       1,930,428.40

491,965.12

   1,001,548.48

King’s Const.

 

Wakarusa Service Center

 

0.00

0.00

0.00

            35,186.00

43,094.00

       (78,280.00)

BWR Planning Consultant

 

Kasold & Peterson Rd Intersection

      300,000

301,050.00

0.00

301,050.00

            21,365.42

119,249.70

      160,434.88

King’s Construction

 

O'Connell Road, WB left turn

      328,960

328,145.00

0.00

328,145.00

            20,928.76

2,977.00

      304,239.24

Peridian Engineering

 

Kasold, Peterson to KTA

      770,000

210,735.00

0.00

210,735.00

          184,477.40

89,563.45

       (63,305.85)

PEC Engineering

Bids Oct. 06

Harvard Rd, East of GWW

      550,000

422,724.00

7,171.56

429,895.56

          440,336.84

0.00

       (10,441.28)

King’s Construction

Complete

2005 Traffic Signal Renovation

      300,000

0.00

0.00

0.00

            16,645.00

0.00

       (16,645.00)

City Staff

 

George Williams Way, 6th to Harvard

   2,500,000

1,663,802.97

3,458.44

1,667,261.41

       1,676,722.48

1,000.00

       (10,461.07)

King’s Construction

 

 

 

 

 

 

 

 

 

 

 

City Hall HVAC 2nd Floor

 

0.00

0.00

0.00

          199,680.00

0.00

     (199,680.00)

Huxtable & Associates

 

19th & Louisiana Traffic Signal

      315,000

59,322.44

0.00

59,322.44

            39,006.79

0.00

        20,315.65

BG Engineering

Study Complete

Bob Billings & Wakarusa

      200,000

200,700.00

0.00

200,700.00

          102,411.25

0.00

        98,288.75

City Staff

 

Public Works Facility - Site Development

      300,000

302,416.01

0.00

302,416.01

          131,561.97

0.00

      170,854.04

BWR Planning Consultant

 

Folks Rd, 6th to Harvard

   1,820,000

1,061,001.00

0.00

1,061,001.00

       1,075,734.26

0.00

       (14,733.26)

R. D. Johnson

Complete

Art Center Expansion

 

 

53,650.29

53,650.29

            15,000.00

0.00

        38,650.29

 

 

Station No 5 Construction

 

0.00

0.00

0.00

                     7.96

0.00

                (7.96)

First Management

 

Investments

 

 

2,216,138.31

2,216,138.31

 

 

   2,216,138.31

 

 

Misc. private projects

 

 

136,389.52

136,389.52

          119,929.40

 

        16,460.12

 

 

Carnegie Rehab - SAT grant

 

0.00

0.00

0.00

            29,267.50

49,632.50

       (78,900.00)

Penny Construction

 

Fire Station #4 2121 Wakarusa

      150,000

2,413,416.00

15,850.00

2,429,266.00

       1,594,590.37

871,194.90

       (36,519.27)

Champion Construction

 

 

 

 

 

 

 

 

 

 

 

 

 

27,922,152.14

5,662,568.79

33,584,720.93

     27,890,505.17

8,002,169.82

  (2,307,954.06)