Memorandum
City
of
Engineering
TO: |
|
CC: |
Terese Gorman |
FROM: |
|
Date: |
|
RE: |
DRAFT 2007 Proposed Contracted Street Repair |
Pavement Management Program Approach, Strategies, & Goal
Life
Cycle Cost (LCC) analysis is an industry standard used by many communities as a
reliable approach for the planning of maintenance activities for streets and is
a key element for an effective Pavement Management Program. The City of
An effective Pavement Management Program focuses on “keeping the good
pavements in good condition”. The goal
of pavement preservation is to:
·
Slow
the deterioration rate of our city streets
·
Extend
the life cycles of our city streets
This can be done effectively through the timely application of
preventative maintenance techniques to postpone pavement failure. Essentially, it is more economical to
preserve the streets than to delay the proper repairs and end up with the need
for minor to major rehabilitation of city streets.
Public Works has taken the approach to address the deterioration of the
streets in good condition by implementing a more aggressive crack sealing
program and by proposing the future use of a substantial amount of
microsurfacing (thin asphaltic surface seal) maintenance work. This, in effect, will slow the deterioration
rate of our “good” streets. We are also
addressing streets that are near the critical point, where preventative
maintenance would be no longer be effective, by performing milling and overlay
and other significant rehabilitation maintenance work. As the program progresses, a greater number
of city streets will be considered in good condition and will be able to be
maintained at a lower cost. As we
increase the inventory of streets rated “good” or better, using these
techniques, additional focus will be placed on the streets that have
deteriorated below the critical range and are in a condition requiring more
expensive maintenance. This program will
allow us to apply more of the funding towards those streets without negatively
impacting the deterioration of our “good” streets. Phasing the repair of heavily deteriorated
streets will not significantly increase the cost due to the expense of the
maintenance that it would already require to bring the pavement up to a
sustainable level.
Another key component of an effective Program is providing appropriate
material and construction specifications.
The Public Works staff has, within the last few years, made changes to
street pavement specifications. For example,
any newly constructed street requires that the pavement subgrade be treated
with fly-ash to provide a more stable foundation for the pavement
material. Also, changes have been made
to the concrete pavement design standard to increase its durability and,
ultimately, extend the life cycle of concrete pavement and curb and
gutter. Currently, the asphaltic
concrete design standards are under review.
These types of actions to ever-improve our design standards will
directly impact the overall longevity of street infrastructure.
Ultimately, the City’s goal for a comprehensive Pavement Management
Program is to provide and maintain a safe and efficient transportation network
through the application of cost-effective maintenance treatments to extend the
overall life of the City’s street infrastructure.
Background
Information
The list of projects for 2007 (as in years past) is developed using a
number of criteria. These criteria
include physical roadway condition, traffic volume, citizen requests for repairs,
and project scope. For this last
criterion, staff determines if the project is presenting on-going maintenance
problems for the street division that cannot be efficiently repaired by City
crews. To aid us in the determination of
physical roadway condition, we are utilizing the Pavement Condition Index (PCI)
ratings that have been collected as part of the Pavement Management System
(PMS). See also (attached separately)
Pavement
Management System & Projected Status
In late October, 2005, the first survey cycle (referred to as Cycle
One) of the street pavement condition inventory for the PMS was completed,
which involved a physical inventory and analysis of every street segment within
the City of
Projected Pavement Condition
Status
The following graph (Figure 1) displays the comparative PCI frequency
distribution for all the streets surveyed from Cycle One analysis through the projected
completion of the 2007 contracted maintenance work (see Proposed Program
Funding – 2007 in this document) that is proposed for the 2007 work year with
the inclusion of applied deterioration rates.
At the end of 2007, it has been projected that the percentage of
streets (yellow bars) that fall within the approximate PCI range of 50 to 70 has
dramatically shifted to the PCI range of 70 to 100. This change is a direct result of the steps
Public Works has taken to crack seal streets and to follow up with planned
patching and microsurfacing treatments, along with other milling and overlaying
maintenance activities. Streets that
have progressed beyond the normal preventative maintenance or simple milling
and overlay period (approximately PCI range of 40 to 50 and below) will be addressed
as soon as funding becomes available to allow for an effective shift in
maintenance focus. This type of
strategy, as discussed earlier in this document, will set the City up for long-term
success to be able to manage and sustain our city streets at a maintainable
level through the use of preservation techniques. This long term goal can be displayed by the
continual positive shift of the percentage of streets to the right side of the
blue “preventative maintenance” line designation.
|
Figure
1 |
The following graphics (Figures 2, 3, & 4) display the improvements
that are being made on the condition of our city street curb and gutter. Upon completion of the projected 2007
contracted work, the City will have replaced over 20 miles of Poor curb and
gutter and 5 miles of adjacent Fair curb and gutter. In turn, and excluding new construction, the
City will have increased the number of miles of Good curb and gutter by
approximately 26 miles or by approximately 4%.
The City has improved their concrete design standard in recent years to
include a more durable concrete composition that will extend the life cycle of
concrete pavement and curb and gutter.
Figure 2
|
Figure 3
|
Figure 4
|
Brick Streets
Within the central part of the City there exist several streets that are exposed brick streets, or brick streets that have been overlaid with asphalt (see attached map). Historically these streets have received maintenance only on an as needed basis due to potholes/significant settling. However, direction is needed on the expectations for these streets. If the asphalt is removed (milled off), it is likely that the bricks will deteriorate significantly. It has not been the City’s recent practice to overlay brick streets once exposed.
Several years ago the Street
Division re-laid a couple blocks on
Photo1
|
Photo 2
|
There are two options to rebuild a brick street:
It is anticipated that when reconstructing a brick street only 50% of the existing bricks will be reusable. An average block (not including the intersections) will use approximately 100,000 bricks at an estimated cost of $2.00 to $3.00 each for brick pavers. This amounts to $100,000 to $150,000 for brick pavers per block.
Commission direction is requested
with respect to how (policy) the City should proceed to improve these
streets. If the Commission desires to
reconstruct a brick street in 2007 additional funding would be required.
Contracted
Street Repair
We have prepared a list of recommended locations for contracted street
repair. Typically, the list of streets
to be repaired is broken into multiple contracts based on the type of work or
combination of work planned, such as:
·
Crack Sealing
·
Chip
and Seal
·
Microsurfacing
·
Milling
and Overlay
·
Curb
and Gutter Repair
·
Pavement
Patching (Asphalt or Concrete Repair)
·
KLINK (Kansas
Department of Transportation Connecting Links Resurfacing Program)
– resurfacing of a State
Highway System route within the City limits
By issuing multiple contracts, the work can be bid by contractors
according to their specialties and can be spread evenly over the construction
season so as to be more manageable for City staff (inspection, project
coordination, etc.). Due to the
significant increase in construction costs, mainly petroleum (asphaltic)
materials, the City will be unable to contract and perform as much maintenance
work as would have been proposed.
Proposed
Program Funding - 2007
The following is a breakdown of the costs associated with the
respective maintenance activity for the proposed
Maintenance Type |
Approximate Construction
Cost |
Crack Sealing |
$300,000 |
Patching & Microsurfacing |
$1,600,000 |
Milling & Overlay |
$2,900,000 |
Curb & Gutter Repair |
$1,200,000 |
PROJECTED TOTAL |
$6,000,000* |
*TOTAL excludes KLINK bonding funds
Please see the attached map
that displays the proposed 2007 maintenance locations, including some additional
planned project locations for future maintenance activities. KLINK locations have not been included.
The following list of street pavement segments that are currently
designated and established as major or main trafficways per City Code 17-501 and
are included in the above proposed 2007 contracted maintenance work:
Street |
From |
To |
Maintenance Type |
Approximate Construction
Cost |
|
|
|
Mill, Overlay, Curb & Gutter |
$300,000 |
|
|
|
Mill, Overlay, Curb & Gutter |
$110,000 |
|
|
|
Mill, Overlay, Curb & Gutter |
$130,000 |
|
|
Iowa St |
Mill, Overlay, Curb & Gutter |
$400,000 |
|
|
Iowa St |
Curb & Gutter |
$90,000 |
PROJECTED TOTAL (Included In Projected Total Above) |
$1,030,000 |
The following pavement segments represent the complete listing of
streets that are planned for Milling & Overlay (M O) and/or Curb &
Gutter Repair (CG) in the
Street |
From |
To |
Cycle One PCI |
Maintenance Type |
Alabama St |
|
|
42 |
M O |
|
|
|
21 |
M O |
|
|
64' N of |
62 |
M O |
|
Maple Ln |
|
46 |
M O CG |
Campfire Ct |
Cul-de-sac |
Campfire Dr |
59 |
M O |
Campfire Dr |
Settlers Dr |
|
42 |
M O |
|
|
Cul-de-sac |
53 |
M O |
|
E 25th Ter |
SEOP |
57 |
M O |
|
Cul-de-sac |
|
55 |
M O CG |
Crescent Rd |
|
10' E of |
41 |
M O |
|
|
|
53 |
M O |
E 18th Ter |
Maple Ln |
Harper St |
57 |
M O |
|
|
Barker Ave |
44 |
M O |
E 21st Ter |
145' S of |
Maple Ln |
50 |
M O |
|
129' E of |
|
58 |
M O |
|
University Dr |
|
51 |
CG |
Frontier Rd |
|
Trail Rd |
46 |
M O |
Hilltop Dr |
|
|
38 |
M O CG |
|
|
|
41 |
M O |
|
|
|
59 |
M O |
|
|
|
35 |
M O CG |
|
|
|
53 |
M O CG |
|
|
|
54 |
M O CG |
|
|
W 19th Ter |
54 |
M O CG |
|
|
|
41 |
M O |
|
W 19th Ter |
|
54 |
M O CG |
|
|
|
54 |
M O |
|
|
|
63 |
M O CG |
|
|
|
47 |
M O |
|
NEOP |
Dakota St |
39 |
M O |
|
Dakota St |
|
42 |
M O |
Pebble Ln |
W 27th Ter |
|
51 |
M O |
Pebble Ln |
|
|
50 |
M O |
|
E 25th Ter |
40' S of |
59 |
M O |
|
|
186' S of |
57 |
M O |
|
|
|
52 |
M O CG |
|
|
|
59 |
M O |
|
Trail Rd |
Cul-de-sac |
56 |
M O CG |
Silicon Ave |
147' S of |
|
50 |
M O |
Trail Rd |
EOP |
|
47 |
M O |
Trail Rd |
125' W of |
Folks Rd |
63 |
M O |
Trail Rd |
|
134' W of |
59 |
M O CG |
Trail Rd |
134' W of |
125' W of |
58 |
M O |
|
|
|
49 |
M O |
|
103' W of |
Iowa St |
59 |
CG |
|
|
|
46 |
M O CG |
|
|
|
51 |
M O CG |
|
|
540' E of |
47 |
M O CG |
|
|
WEOP |
53 |
M O |
W 27th Ter |
136' E of |
|
53 |
M O |
|
30' W of |
|
43 |
M O CG |
|
|
31.5' W of Missouri St |
44 |
M O CG |
Street |
From |
To |
Cycle One PCI |
Maintenance Type |
|
31.5' W of Missouri St |
30' W of |
46 |
M O CG |
|
|
|
58 |
M O CG |
|
|
|
40 |
M O CG |
|
|
|
62 |
M O CG |
|
90' E of |
528' E of |
66 |
M O |
|
|
90' E of |
58 |
M O |
|
528' E of |
Iowa St |
55 |
M O |
|
|
Cul-de-sac |
47 |
M O |
|
W Hills Ter |
Crescent Rd |
47 |
M O |
|
|
|
53 |
CG |
|
|
|
56 |
CG |
|
Frontier Rd |
Cul-de-sac |
48 |
M O |
|
Cul-de-sac |
Frontier Rd |
46 |
M O |
|
|
Iowa St |
38 |
M O CG |
|
|
|
56 |
M O |
|
|
|
56 |
M O CG |