Memorandum

City of Lawrence

Utilities Department

 

TO:

Dave Corliss

FROM:

Philip Ciesielski

CC:

Debbie Van Saun

Dave Wagner

Chris Stewart

Michael Tubbs

Dave King

Date:

July 5, 2006

RE:

Preliminary Agreement for Design/Build Services for Pump Station 48 – formerly Baldwin Creek 1 Pump Station 1

 

Please include the following item on the City Commission consent agenda for consideration at the July 11, 2006 meeting:

Enter into a design/build services contract with the design/build team of CAS Construction/Professional Engineering Consultants in the amount of $403,000.00 for preliminary design/build services for the construction of Pump Station 48, its associated forcemain and a portion of the upstream gravity sewer network in accordance with recommendations in the 2003 Wastewater Master Plan and direction provided by the City Commission on April 11, 2006.

 

Summary.  Staff has negotiated a contract for preliminary design/build services with the CAS Construction/Professional Engineering Consultants design/build team.  After satisfactory completion of the preliminary design/build services the Utilities Department anticipates amending the contract with the CAS Construction/Professional Engineering Consultants design/build team, based on a lump sum established during the preliminary design/build services phase, for final design and construction of the project.

Project Description.  The project involves the design and construction of the sanitary sewer pump station identified in the 2003 Wastewater Master Plan as BC1PS1, currently designated Pump Station 48, its associated forcemain and a portion of the upstream gravity sewer network.  This project was recommended as part of the adopted 2003 Wastewater Master Plan.  

 

Project History.  Based on the growth projections used in the 2003 Wastewater Master Plan these facilities were scheduled to be constructed in 2010.  Growth in the area has progressed at a pace in excess of that identified in the 2003 Wastewater Master Plan.  On April 11, 2006 staff presented information to the City Commission regarding the growth in this area and the need for the City to accelerate, and participate in, this project.  Staff was directed to advertise for proposals for design/build services to complete the project.

 

Project Status.  On April 13, 2006 the Utilities Department solicited proposals for design/build services for the design and construction of Pump Station 48, its associated forcemain and a portion of the upstream gravity sewer network.

 

On Monday May 1, 2006, in response to the Request for Proposals, the Utilities Department Staff received proposals from three design-build teams.  Proposals were received from Burns & McDonnell/Garney LLC, CDM/Wolf Construction, and CAS Construction/Professional Engineering Consultants.  

 

A review committee consisting of Department of Utilities staff evaluated the three proposals.  Staff consistently ranked CAS Construction/Professional Engineering Consultants as the highest qualified team.  The following criteria were used:

 

Related Design/Build Lift Station and Piping Project Experience

Project Team

Project Approach

Project Schedule

Technical Capabilities

Client References

Past Experience with the City of Lawrence

 

On May 16, 2006 the City Commission authorized staff to negotiate a design/build contract with CAS Construction/Professional Engineering Consultants.

 

On June 20, 2006 the City Commission authorized staff to proceed, during the negotiation of the preliminary design/build services agreement, directly with Professional Engineering Consultants in the amount of $290,800.00 to perform preliminary field investigative work items critical to maintaining the current aggressive design/build schedule.

 

Staff has negotiated the contract for preliminary design/build services with the CAS Construction/ Professional Engineering Consultants team as the first part of the project.  After satisfactory completion of the preliminary design/build services phase the Utilities Department anticipates amending the contract with CAS Construction/Professional Engineering Consultants, based on a lump sum established during the Preliminary Agreement, for final design and construction of the project.

 

Staff anticipates bringing additional project items to the City Commission for consideration over the next few months regarding property acquisition and easements, and authorization of a final design/build contract based on the lump sum generated during the current preliminary phase. 

 

Project Funding.  Funding for the project will ultimately be shared by development benefiting from this infrastructure improvement through the payment of special connection charges and the City-at-large for that portion of the project that benefits the existing sanitary sewer system.

 

Action Request.  Utilities Department staff requests authorization for the City Manager to enter into a design/build services contract with the CAS Construction/Professional Engineering Consultants team in the amount of $403,000.00 for the preliminary design/build services for Pump Station 48, its associated forcemain and a portion of the upstream gravity sewer network in accordance with recommendations in the 2003 Wastewater Master Plan and as directed by the City Commission on April 11, 2006.