Memorandum
City of Lawrence
Engineering
TO:
|
Chuck Soules
|
FROM:
|
Terese Gorman
|
CC:
|
Steve Lashley
|
Date:
|
July 5, 2006
|
RE:
|
Project Update
|
There are numerous construction projects occurring for new subdivisions
or new development which do not impact the traveling public. The following projects impact existing
streets and traffic.
Kasold Drive, Bob Billings Parkway
to 22nd Street. The west half of Kasold is
closed and currently there is one lane of traffic in each direction for
northbound and southbound drivers. This
project will not be completed this summer. The estimated completion date is Fall 2007.
Monterey Way
– Peterson Road. Monterey Way is
open to traffic between Stetson
Drive and Grand Vista Drive. The intersection of Peterson Road and Kasold Drive is currently being
reconstructed. One lane of traffic is
allowed northbound and southbound on Kasold.
Peterson Road,
between Monterey Way
and Kasold Drive,
is closed to all traffic. The estimated
completion date to have Peterson
Road and the intersection open to all traffic is
October 1, 2006.
23rd Street and
Iowa Street, has been milled and full depth patching is occurring. Currently, 23rd Street has one lane of
traffic each direction. 23rd Street
will be paved during the day the week of July 10. Iowa
Street milling will begin on July 10. Paving will occur the week of July 23. This project will be completed by August 1.
Overlay,
Phase 1.
This project is currently 60% complete.
The following streets have been completed:
Atchison Avenue, Clinton
Parkway to 26th Street
Clinton Parkway frontage road, Hawthorne Drive to Crossgate Drive
Hawthorne Drive, Clinton
Parkway to Lowell Drive
Lowell Drive, Clinton
Parkway to Hawthorne Drive
Maverick Lane, 27th Street
to 28th Terrace
Morningside Drive, Brush Creek Drive to cul-de-sac,
including Morningside Court
Ranch Street, west of Inverness Drive
W. 11th Street, Mississippi to West Campus Road
W. 24th Street, Ridge Court to Iowa Street
W. 24th
Terrace, Crossgate
Drive to cul-de-sac
W. 25th Street, Cedarwood Avenue
to Ridge Court
W. 2nd Street, Michigan to McDonald Drive
The following streets are currently under construction:
Inverness Drive, Wakarusa Drive to Bob Billings Parkway
including Bel-Air
Court, Royal
Birkdale Court, Winged Foot Court
Murrow Court, 9th Street
to Yale Road
Riverview Road, Settlers Drive to Kasold Drive
Rockfence Place,
Longhorn Drive
to Riverview Road
N. 7th Street, Walnut Street to Lake Street
Wagon Wheel Road, Longhorn Drive to Riverview Road
Inverness
Drive will be completed by August 1.
The remaining streets will be completed in late August or September.
Overlay
and Curb Repair, Phase 2.
This project is currently 20% complete.
The following streets have been completed:
Bob Billings Parkway, Inverness
to Wakarusa Drive
Flint Drive, 26th Street to Atchison Avenue
The following streets are currently under construction:
Clinton Parkway
frontage road, Crossgate
Drive to Bishop Seabury
Naismith Drive (northbound), 19th
Terrace to 23rd Street
Tennessee, 19th Street to 23rd Street
21st Street, Tennessee
to Louisiana
27th Street, Iowa to Lawrence Avenue
Construction has not begun on the following streets:
Cambridge Road, High Drive to Sunset Drive
Crestline Drive, 9th to Yale Road
Glenview Drive, Summertree Lane
to Peterson Road
14th Street, Massachusetts
to Kentucky
9th Terrace, Rockledge Road to Crestline Drive
Woodgate Place,
Creekwood
Drive to Princeton
Boulevard
Cambridge Road, Crestline
Drive, Naismith
Drive and 14th Street will be completed
by August 1.
Overlay
and Curb Repair, Phase 3.
This project has just begun. The
contractor is currently working on Greenway
Circle and East Hills Drive. The other streets included in this project
are: Haskell Avenue, 15th Street to 23rd Street;
Maple Lane,
Brook Street to 19th Street; W. 5th Street, Indiana to Maine; E. 19th Street,
Massachusetts to Rhode Island. E. 19th
Street will be completed by August 1.
Sidewalk
Inventory.
Currently, the sidewalk inventory is approximately 40% complete. The inventory has been completed in North
Lawrence, all of the area east of Iowa and
north of 23rd Street
to the east city limits, and the area west of Iowa to Kasold Drive between 6th Street and 15th Street. There are two interns this summer who are
collecting the data and entering it into a database. A sample of the inventory rating sheet is
attached, as well as several pictures of sidewalk conditions that are being
found.
Attached are five pictures of damaged sidewalks:
- Critical
overgrowth on the east side of 4th
from Elm to Walnut,
- Critical
overgrowth and cracking on the east side of Wellington
from Harvard to Steven
Drive,
- Critical
cracking on the west side of Massachusetts from
23rd Street
to south end,
- Critical
deflections and cracking on the east side of Mississippi from
3rd Street
to 4th Street,
- Critical
overgrowth on west side of Connecticut from
7th Street
to 8th Street.