CITY OF LAWRENCE |
|
|
|
|
|
|
|
|
|
|
|
Project No. 12-SR5-306(C) |
|
|
City Bid No. B06016 |
|
|
2006 Overlay and Curb Repair
Program, Phase 3 |
|
|
|
|
|
BID TAB |
|
|
Bid Date: May 23, 2006 |
|
|
Engineer's Estimate: $1,164,293.50 |
|
|
Kansas Heavy
Construction |
LRM Industries, Inc. |
|
|
ITEM |
DESCRIPTION |
UNITS |
QUANTITY |
UNIT PRICE |
AMOUNT |
UNIT PRICE |
AMOUNT |
|
1 |
Milling
(2") |
SY |
47,515 |
$
1.90 |
$ 90,278.50 |
$ 1.90 |
$ 90,278.50 |
|
|
|
|
2 |
Asphaltic
Concrete Overlay (2") (BM-2) |
TONS |
3,155 |
$
47.60 |
$ 150,178.00 |
$ 45.00 |
$ 141,975.00 |
|
|
|
|
3 |
Asphaltic
Concrete Overlay (2") (BM-2 Special) |
TONS |
2,334 |
$
49.25 |
$ 114,949.50 |
$ 50.00 |
$ 116,700.00 |
|
|
|
|
4 |
Asphaltic
Concrete Pavement Patch (full depth) (BM-2)* |
TONS |
633 |
$
95.00 |
$ 60,135.00 |
$ 95.00 |
$ 60,135.00 |
|
|
|
|
5 |
Concrete Pavement Patch (full
depth)* |
SY |
871 |
$
70.00 |
$ 60,970.00 |
$ 77.50 |
$ 67,502.50 |
|
|
|
|
6 |
6"
Concrete Pavement (Reinforced) |
SY |
846 |
$
49.70 |
$ 42,046.20 |
$ 45.75 |
$ 38,704.50 |
|
|
|
|
7 |
8"
Concrete Pavement (Reinforced) |
SY |
145 |
$
72.00 |
$ 10,440.00 |
$ 55.85 |
$ 8,098.25 |
|
|
|
|
8 |
24"
Concrete Curb & Gutter (8" toe) |
LF |
22,776 |
$
18.00 |
$ 409,968.00 |
$ 18.40 |
$
419,078.40 |
|
|
|
|
9 |
4"
Concrete Sidewalk |
SY |
16 |
$
30.00 |
$ 480.00 |
$ 47.00 |
$ 752.00 |
|
|
|
|
10 |
6'x4'
Curb Inlet |
EACH |
3 |
$
3,600.00 |
$ 10,800.00 |
$
3,625.00 |
$ 10,875.00 |
|
|
|
|
11 |
7.5'x4'
Curb Inlet Top (Retrofit) |
EACH |
1 |
$
1,300.00 |
$ 1,300.00 |
$
1,690.00 |
$ 1,690.00 |
|
|
|
|
12 |
6.5'x6'
Curb Inlet Top (Retrofit) |
EACH |
1 |
$
1,200.00 |
$ 1,200.00 |
$
1,690.00 |
$ 1,690.00 |
|
|
|
|
13 |
6'x5.5'
Curb Inlet Top (Retrofit) |
EACH |
1 |
$
1,200.00 |
$ 1,200.00 |
$
1,690.00 |
$ 1,690.00 |
|
|
|
|
14 |
6'x4'
Curb Inlet Top (Retrofit) |
EACH |
6 |
$
1,200.00 |
$ 7,200.00 |
$
1,690.00 |
$ 10,140.00 |
|
|
|
|
15 |
6'x3.5'
Curb Inlet Top (Retrofit) |
EACH |
1 |
$
1,100.00 |
$ 1,100.00 |
$
1,690.00 |
$ 1,690.00 |
|
|
|
|
16 |
Crackfilling
* |
LF |
31,885 |
$
0.60 |
$ 19,131.00 |
$ 0.60 |
$ 19,131.00 |
|
|
|
|
17 |
Pavement
Crack/Joint Membrane * |
LF |
31,885 |
$
1.55 |
$ 49,421.75 |
$ 1.55 |
$ 49,421.75 |
|
|
|
|
18 |
Manhole
Adjustment |
EACH |
10 |
$
700.00 |
$ 7,000.00 |
$
650.00 |
$ 6,500.00 |
|
|
|
|
19 |
Valve
Adjustment |
EACH |
17 |
$
260.00 |
$ 4,420.00 |
$
200.00 |
$ 3,400.00 |
|
|
|
|
20 |
Cold
Plastic Reflectorized Pavement Marking |
|
|
|
|
|
|
|
|
|
|
|
a) 24" Solid White Stop Line (class A) |
LF |
117 |
$
14.00 |
$ 1,638.00 |
$ 14.00 |
$ 1,638.00 |
|
|
|
|
|
b) 36" Solid White Crosswalk Line (class
A) |
LF |
243 |
$
18.00 |
$ 4,374.00 |
$ 18.00 |
$ 4,374.00 |
|
|
|
|
|
c) 6" Dotted White Lane Line (class A) |
LF |
254 |
$
4.00 |
$ 1,016.00 |
$ 4.00 |
$ 1,016.00 |
|
|
|
|
|
d) 6" Solid White Channelization Line
(class A) |
LF |
1,134 |
$
4.00 |
$ 4,536.00 |
$ 4.00 |
$ 4,536.00 |
|
|
|
|
|
e) 12" Solid White Chevron Line (class A) |
LF |
72 |
$
10.50 |
$ 756.00 |
$ 10.50 |
$ 756.00 |
|
|
|
|
|
f) Left Turn Lane - Use Arrow |
EACH |
10 |
$
350.00 |
$ 3,500.00 |
$
350.00 |
$ 3,500.00 |
|
|
|
|
|
g)
Right Turn Lane - Use Arrow |
EACH |
2 |
$
350.00 |
$ 700.00 |
$
350.00 |
$ 700.00 |
|
|
|
|
|
h) 6" Broken Yellow Lane Line (class B) |
LF |
960 |
$
4.25 |
$ 4,080.00 |
$ 4.25 |
$ 4,080.00 |
|
|
|
|
|
i) 4" Solid Double Yellow Lane Line
(class B)** |
LF |
1,393 |
$
5.00 |
$ 6,965.00 |
$ 5.00 |
$ 6,965.00 |
|
|
|
|
21 |
Traffic Signal Loops |
LF |
968 |
$
11.25 |
$ 10,890.00 |
$ 10.85 |
$ 10,502.80 |
|
|
|
|
22 |
Temporary Surfacing* |
TONS |
50 |
$
24.00 |
$ 1,200.00 |
$ 20.00 |
$ 1,000.00 |
|
|
|
|
23 |
Traffic Control |
LS |
1 |
$
38,000.00 |
$ 38,000.00 |
$
28,400.00 |
$ 28,400.00 |
|
|
|
|
24 |
Seed,
Fertilize, & Mulch |
LS |
1 |
$
7,627.05 |
$ 7,627.05 |
$
12,960.00 |
$ 12,960.00 |
|
|
|
|
|
GRAND TOTAL |
|
|
$ 1,127,500.00 |
|
$ 1,129,879.70 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|