City of Lawrence

Neighborhood Resources Department

 

MEMORANDUM

 

 

TO:              David L. Corliss, Interim City Manager

 

THRU:                   Margene Swarts, Community Development Manager

 

FROM:         Tony L. Hoch, Projects Specialist

 

DATE:           May 31, 2006

 

STAFF PRESENT FOR BID OPENING on April 25, 2006:  Tony L. Hoch, Larry E. Hamm, Alan Landis, Frank Reeb.

 

COMPREHENSIVE HOUSING REHABILITATION SCOPE OF WORK:

 

1619 E 18th Street:  Partial siding replacement and painting,  driveway replacement, garage door replacement, window repairs, minor door repairs, laundry drain, furnace and water heater replacement, kitchen sink replacement and countertop GFCI’s, ceiling fan boxes, carpet replacement in hall and adjoining living room.

 

 

 

CONTRACTOR

1619 E 18th Street

Penny Construction, Inc.

$16,346.00

T & J Holdings, Inc.

$17,065.50

Staff Estimate

$22,531.5

 

Recommendation Action:

 

Staff recommends award of bid as follows:

 

1619 E 18th Street: Penny Construction, Inc.

 

 

 

cc:      Bobbie Walthall

          Frank Reeb

          Alan Landis