City of Lawrence | ||||||||||
2007-2012 Capital Improvement Plan | ||||||||||
Table 12c. Anticipated Funding Sources - 2012 Projects | ||||||||||
ANTICIPATED FUNDING SOURCES | ||||||||||
DEPT. | PROJECT TITLE | G.O. BONDS | SPEC. ASSMNTS |
REVENUE BONDS* | CURRENT REVENUE | FEDERAL AID | STATE AID | OTHER | 2012 TOTAL (000S) | |
PW | 23rd and Ousdahl | 1,500 | 1,500.0 | |||||||
PW | W 15th & SLT Interchange | 5,000 | 5,000 | 10,000.0 | ||||||
Public | Wakarusa Clinton to SLT - Bike/Ped. | 75 | 75.0 | |||||||
P&R | Park and Open Space Aquistion | 300 | 300.0 | |||||||
Airport | Rehabilitate Airfield Pavements | 1,500 | 1,500.0 | |||||||
PW | 5th & Maple Pump Station | 4,000 | 4,000.0 | |||||||
PW | Maple Ln - 19th to Brook | 2,428 | 2,428.0 | |||||||
PW | 16th St - Kentucky to Rhode Island | 6,174 | 6,174.0 | |||||||
PW | W. 11th & Alabama | 1,140 | 1,140.0 | |||||||
PW | KLINK | 500 | 200 | 700.0 | ||||||
PW | North St - N 2nd to N 7th St. | 2,000 | 2,000.0 | |||||||
PW | 15th and Haskell - Roundabout | 780 | 780.0 | |||||||
PW | NR 1000 BLK Tenn. Stone Curb | 150 | 150.0 | |||||||
FM | Fire Medical Station No. 8 - Southeast, Const. | 3,272 | 3,272.0 | |||||||
FM | Fire Medical Station No. 9 - North Lawrence/Airport, Construction | 3,272 | 3,272.0 | |||||||
Transit | Paratransit (T-Lift) Bus Replacement (2 vehicles) | 140 | 140.0 | |||||||
P&R | Develop Park W. of Clinton WTP | 200 | - | |||||||
Airport | Construct Access Taxiways to Executive Hangars | 110 | 110.0 | |||||||
Airport | Construct Access Taxiways to T-Hangars | 162.5 | 162.5 | |||||||
P&R | Neighborhood Spray Park | 200.0 | 200.0 | |||||||
Utilities | Clinton WTP Supply Expansion - 3 new pumps - cont from '11 | - | ||||||||
Utilities | Replace watermain 9th & NY to 19th & Harper | 2,049.6 | 2,049.6 | |||||||
Utilities | Kanwaka Tank | 2,049.6 | 2,049.6 | |||||||
Utilities | Waterline Rehab & Replacement | 1,365.9 | 1,365.9 | |||||||
Utilities | Misc Water System Improvements | 1,365.9 | 1,365.9 | |||||||
Utilities | I/I Removal | 890 | 890.0 | |||||||
Utilities | General Sanitary Sewer Improvements | 822 | 822.0 | |||||||
Utilities | General Pumping Station Improvements | 274 | 274.0 | |||||||
Utilities | General WWTP Improvements | 274 | 274.0 | |||||||
TOTAL FOR ALL PROJECTS | 32,764 | - | 9,091 | 140 | 5,000 | 200 | - | 47,194.5 | ||
*Water and Wastewater Master Plan calls for issuing Revenue Bonds in odd numbered years. Bonds required for 2008 projects were issued in the previous year. | ||||||||||