April 25, 2006 Agenda Item City Project No. 36-CP12-704(S) Kasold Drive, Peterson Road to the KTA Bridge KDOT Project No. 23 U-2040-01 Engineering Contract Amendment #2
|
Please include the following item on the City Commission regular agenda for consideration at the April 25, 2006 meeting:
Project History.
April 13, 2004 |
City Commission places the construction of Kasold Drive, Peterson to KTA on 5-Year Plan |
September 7, 2004 |
City Commission approves Engineering Contract with Professional Engineering Consultants |
November 18, 2005 |
Open house with neighbors. |
January 11, 2005 |
Alternatives presented to City Commission. |
January 18, 2005 |
Revised alternatives presented to City Commission. Direction to proceed with Option R-1
|
March 8, 2005 |
City Commission approves amendment to contract with PEC for Option R-1. |
December 18, 2005 |
Open house with neighbors. |
Project Bid Schedule |
October 2006 |
Project Description. The road will be a wide two-lane facility with roundabouts at Tillerman Drive and Grand Vista Drive. A wide median will be constructed with access at each intersection. Alternate Option R-1 can be viewed at
http://www.lawrencepublicworks.org/kasold_north/Alt_R1.jpg
Project Status. The project has been submitted to KDOT for final plan review. The projected schedule for bidding is October 2006; however, pending progress on the 2nd and Locust project, this project may get moved to a 2007 letting.
Project Funding. Current construction estimate is $3,300,000. The State (KDOT) will participate up to $2.7 million with a City share of approximately $600,000 (this does not include the water main, engineering, or right-of-way costs).
Engineering Costs: |
Original contract |
$162,460 |
|
Amendment #1 for additional options and public involvement |
$ 44,000 |
|
Amendment #2 for landscaping, lighting, right-of-way staking (see attached amendment). |
$ 46,600 |
Action Request. Pending City Commission discussion, approve Contract Amendment No. 2 with Professional Engineering Consultants for engineering services for Kasold Drive, Peterson Road to KTA Bridge, City Project No. 36-CP12-704(S).