CITY OF LAWRENCE, NEIGHBORHOOD RESOURC Date:__3/22/06_______

                                                         SPECS BY LOCATION/TRADE with Costs

        Work Write-up/Re-Bid:      ___________                                                Initial:  ____________         Case No:  _____________        1

        Walk Through Date:           ___________

        Bid Date:                                  ___________

        Construction Specialist:Tony  Hoch               Phone:  785-832-3113

 

     Project:      CRP032206                             Address:   429 INDIANA Street                                  Unit:     1

 

     Location:  1  General Requirements

 

     Spec                                                                                                                                                                                                Unit                  Total

     Number       Spec                                                                                                                         Quantity        Units        Price                  Price

     Trade:     1           General Requirements

 

     2.1                     GENERAL PROJECT NOTES

     Where applicable, owner will choose paint colors, vinyl sheet goods, kitchen cabinet styles and colors, and light fixtures. Allowances for materials will be as follows:

    1.  Vinyl sheet goods - $ 2.00 per square foot.

    2.  Carpet goods - $ 2.00 per square foot.

    3.  Light fixtures - $40.00 per fixture.

   

    General Contractor  will be responsible for the moving of all furniture and all appliances.  The Contractor will be responsible for

    any damage to furniture and the replacement of all furniture to its original location.  Cover all furniture for protection of

    finish.  Also, all carpets will be covered and protected from construction trash.

   

    All construction trash shall be kept cleaned up at all times.  All plumbing and electrical work must be done by a licensed

    plumber and electrician.  All work shall meet or exceed city codes of the City of Lawrence.  Permits are required and

    inspections are required by the City Inspectors.  The General Contractor is responsible for repairs of wall, ceiling, and

    floor damage caused by subcontractors.

   

    All equivalent or equal items will have to be approved by Neighborhood Resources Department representative, Contractor,

    and applicant together.  NO EXCEPTIONS.

   

    Please pay special attention to all parts of the "Specifications by Location and Trade".  This document will explain, in more

    detail, about workmanship and what is expected for a quality job.

                                                                                                                                                                      1.00       AL                       $0.00                  $0.00

     35.1                  VERIFY QUANTITIES/MEASUREMENTS

     All measurements (i.e SF of Drywall, or those provided with drawings) are for the contractor's convenience prior to a mandatory

    site inspection to verify all dimensions.  All quantities (i.e.number of window units) are as stated.  No claim for additional

    funds due to discrepancies in measurements or quantities shall be honored if not submitted at the time of the initial proposal.

                                                                                                                                                                      1.00       GR                      $0.00                  $0.00

     36.1                  BUILDING PERMITS REQUIRED

     The contractor is responsible for submitting a copy of this Neighborhood Resources Department prepared work write up, to the

    Building Inspeciton Department, applying for, paying for and receiving required permits prior to starting any work.

    Contractors are responsible for calling for code required inspections, and closing all permits before payments are made.

                                                                                                                                                                      1.00       EA                      $0.00                  $0.00

     77.1                  NEW MATERIALS REQUIRED

     All materials used in connection with this work write-up are to be new, of first quality and without defects - unless stated

    otherwise or pre-approved by Owner and Construction Specialist.

                                                                                                                                                                      1.00       GR                      $0.00                  $0.00

     90.1                  1 YEAR GENERAL WARRANTY

     Contractor shall remedy any defect due to faulty material or workmanship and pay for all damage to other work resulting

    therefrom, which appear within one year from final payment.  Further, contractor shall furnish owner with all manufacturers'

    and suppliers' written warranties covering items furnished under this contract prior to release of the final payment.

                                                                                                                                                                      1.00       DU                      $0.00                  $0.00

     Trade:     9           Environmental Rehab

 

     9003.1              LEAD ABATE. STAND. & GUIDELINES

     The execution of this work shall comply with all applicable state, federal and local laws, rules, regulations and

    guidelines.  Some of these standards include: 29 CFR 1926-Construc- tion Industry Standards, 29 CFR 1926.62-Con-

    struction Industry Lead Standard, 29 CFR1910. 1200-Hazard Communication, 40 CFR Part261-EPA Regulations, NCLSH-HUD Lead Paint Guidelines for residential structures.

                                                                                                                                                                      1.00                                   $0.00                  $0.00

     9007.1              CLEAN TO CLEARANCE

     Prior to final acceptance of the lead hazard reduction work and all rehabilitation work, the property shall be visually

    inspected for any remaining paint chips, dust and debris and lead dust wipe samples shall be obtained from floors, windows

    sills and window troughs.  The contractor shall re-clean all applicable components and surfaces and pay for all additional

    clearance dust sampling if any dust sample results exceedd the thresholds of 40 ug/SF for floors, 250 ug/Sf for window sills

    and 400 ug/SF for window troughs.

                                                                                                                                                                  800.00       SF                      $1.25          $1,000.00

     9023.1              CLEARANCE EXAMINATION

     Using a trained and certified lead paint inspector, a lead hazard risk assessor, or if approved, a sampling technician, one hour after completion of all lead hazard reduction, renovation and maintenance work, conduct a visual assessment for evidence of remaining paint chips, visible dust debris and residue.  Randomly select four (4) floors, two (2) window sills and two (2) window troughs to dust wipe test as per protocol in the HUD Guidelines.  Submit the dust samples, plus a blank sample, to an EPA-accredited lead analytical laboratory for determination of lead content.  Provide the owner, occupants and this agency with the clearance report and a "Notice of Lead Hazard Reduction" within 15 days of achieving final clearance, in accordance with 23 CFR Part 35.

                                                                                                                                                                      1.00       EA                 $500.00              $500.00

 

                                                                                                              Totals for Location:  1  General Requirements:          $1,500.00

     Location:  2  Exterior

 

     Spec                                                                                                                                                                                                Unit                  Total

     Number       Spec                                                                                                                         Quantity        Units        Price                  Price

 

     Trade:     5           Demolition & Disposal

 

     715.1                GUT STRUCTURE INTERIOR

     Remove all wall framing, floor and wall finishes, windows, doors, trim, equipment, debris and household items from structure

    and dispose of in legal landfill.  Broom sweep all floors and rake yard areas.

                                                                                                                                                                  800.00       SF                      $5.00          $4,000.00

     750.1                DEMO OUTBUILDING

     Disconnect and cap off all electrical and plumbing services.  Demolish outbuilding to below grade and dispose of debris in

    code legal dump.Rake yard clean including nails and glass.

                                                                                                                                                                  100.00       SF                      $3.00              $300.00

     Trade:     6           Concrete & Paving

 

     1033.1              CONCRETE SIDEWALK CITY

     Remove old damaged sidewalk.  Replace the sidewalk in a manner which will comply with all aspects of the "City of

    Lawrence Residential Sidewalk Requirements" adopted by the City Commission, July 10th, 1996.  Remove all forms, regrade

    and spot seed.

                           Finish last 7' on south end of brick walk way.

                                                                                                                                                                    21.00       SF                    $15.00              $315.00

     1034.1              CONCRETE SIDEWALK HOMEOWNER

     Form and pour 4" thick, 2200 psi concrete slab including all form work, 6 mil vapor barrier, 4" gravel base, 10x10 wire mesh

    and a steel trowel finish.  Remove all forms, regrade and spot seed.

                           INCLUDE YARD STEPS

                                                                                                                                                                  120.00       SF                      $6.00              $720.00

     1050.1              CONCRETE RETAINING WALL

     Excavate side of hill to allow space to arrange formwork. Place 8"x16" cont. strip ftg. below frost line w/2-#2 rebars 2.5" min.

    from edges. Build forms for walls, min 8" thick, w/a batter 7 deg. toward hill from horiz. Place #4 rebar 48" o.c. vert. &

    horiz. & tie into ftg @ keyway. Pour & vibrate 2,500 psi conc. min. 3000 psi rec.  Allow weep holes @48" o.c. @ lowest grade.

    Strip forms & backfill w/pea gravel. Restore topsoil & seed.

                                                                                                                                                                    51.00       SF                    $21.00          $1,071.00

     855.1                DEMO CONCRETE

     Break up concrete and remove off site to code legal dump.

                                                                                                                                                                    80.00       SF                      $2.50              $200.00

     865.1                FOOTING--PIER

     Excavate a square, straight sided hole below the frost line to solid bearing.  Pour a 24" x24"x18"pier footing with two #5

    reinforcing rods.  Cast a rod to anchor pier.

                           FOR BEAM SUPPORTS ON REAR ROOMS

                                                                                                                                                                      4.00       EA                 $165.00              $660.00

     870.1                FOOTING--CONTINUOUS

     Excavate a square, straightened, trench below frost line to solid bearing.  Form and pour a 2500 psi, 18"x9" deep footing

    reinforced with at least two #4 rebar securly wired and set on chairs.  Remove forms after concrete has fully cured.

                           JACK AND SUPPORT HOUSE UNDER BLOCK FOUDATION.  REMOVE BLOCK FOUNDATION.

                                                                                                                                                                    86.00       LF                     $40.00          $3,440.00

     Trade:     7           Masonry

 

     1105.1              FOUNDATON--PARGET

     Parget foundation wall with 3/8" coat of waterproof cement.  Match existing finish as closely as possible.

                                                                                                                                                                  200.00       SF                      $1.10              $220.00

     1110.1              BLOCK FOUNDATION WALL

     Construct an 8"x 16"x 8" thick, reinforced cement block wall with trowel cut joints, 1/2" exterior waterproof pargeting, and a

    solid cap block.

                                                                                                                                                                  588.00       SF                      $7.00          $4,116.00

     Trade:     8           Metal Work

 

     1460.1              METAL GUARD RAIL--WROUGHT

     Design, fabricate, prime, topcoat and install a one-piece steel railing of 2" flat top and bottom rails and 1/4" balustrades 6" on

    center.

                           FOR BASEMENT STAIR ENTRANCE.

                                                                                                                                                                    14.00       LF                     $56.00              $784.00

     Trade:     10         Carpentry

 

     2600.1              SIDING--T1-11

     Remove existing siding, Install rough sawn fir, 1/2" thick, factory stained, T1-11 siding sheets, 1"x 3" trim at corners.  Use

    lap flashing on horizontal seams. Flash or install silicone caulking along entire top edge, and under windows or other

    openings.

                                                                                                                                                              1,200.00       SF                      $5.00          $6,000.00

     2980.1              WINDOW--VINYL - DBL GLZ

     Field measure, order and install a like functioning vinyl, double glazed, replacement window and jamb including screen, caulk,

    interior casing and exterior trim.  If applicable, provide snap-in or internal grill to match mullion pattern of other openings.

                                                                                                                                                                      2.00       EA                 $600.00          $1,200.00

     3560.1              PORCH--REBUILD

     Remove deteriorated porch.  Construct 12"x 12" masonry piers, 2"x 10" joists with 3/4" tongue and groove flooring to support

    child-proof wood railing and 4"x 4" posts for roof. Construct roof structure with 2"x 6" rafters, 1/2" plywood deck, fiberglass

    shingles, aluminum gutter and downspouts and 1/4" plywood ceiling.  Structural lumber and deck shall be preservative

    treated.

                                                                                                                                                                  140.00       SF                    $26.00          $3,640.00

     3590.1              STEPS/LANDING--REPL EXTERIOR

     Dispose of existing steps and landing. Construct a replacement unit with two 2"x 12" preservative treated pine stringers,

    5/4" PTP stepping stock treads, on a solid concrete footer.  Frame stairs 3' wide connecting to porch. Construct a wood

    handrail on one side 32" above tread nosing.

                                                                                                                                                                      1.00       EA                 $280.00              $280.00

     Trade:     15         Roofing

 

     4490.1              ROOF SHEATHING 1/2"

     Remove Sheathing and Install 1/2" CDX plywood sheathing nailed 8" on center using plywood clips.

                                                                                                                                                              1,000.00       SF                      $2.10          $2,100.00

     4525.1              ROOF--90 LB. ROLL

     Install 90 lb. mineralized fiberglass roll roofing using a 4" minimum overlap, nailed 6" on center with asphalt roofing cement

    per manufacturer's specs.  Replace all flashing with .019 aluminum.

                                                                                                                                                                      4.50       SQ                 $225.00          $1,012.50


 

     4580.1              TEAR OFF AND REROOF SHINGLES

     Remove and dispose of all roofing & defective sheathing.  Cut a 1" wide vent at ridge board. Allow for replacement of up to 5 sf

    of sheathing per 100 sf of roof using pine board or CDX plywood of matching thickness.  Install 15 lb felt. Install preformed and

    prefinished drip edge, and vent pipe boots. Install a 220 lb fiberglass asphalt, 3 tab shingle with a 25 yr warranty. Replace all

    flashing. Install shingle-over ridge vent.

                                                                                                                                                                      7.00       SQ                 $225.00          $1,575.00

     4635.1              GUTTER--5" SEAMLESS ALUMINUM

     Dispose of gutter.  Install 5", K- type, seamless, .027 gauge aluminum gutter to service roof.  White or color choice by owner.

                                                                                                                                                                    80.00       LF                       $5.00              $400.00

     4640.1              DOWNSPOUT--5" SEAMLESS ALUMINUM

     Dispose of downspout.  Install 5", square, seamless, .027 gauge, aluminum downspout.  Strap at least 3' on center.  White or

    color choice by owner.

                           AT 4 LOCATIONS

                                                                                                                                                                    50.00       LF                       $4.00              $200.00

     4665.1              SPLASH BLOCK

     Place concrete or plastic splash block at end of downspout.

                                                                                                                                                                      4.00       EA                    $20.00                $80.00

     4755.1              FASCIA 1"X 6"

     Install a 1"x 6", #2 pine fascia with bevel cut joints using galvanized finish nails. Caulk over joints, and prime.

                                                                                                                                                                  150.00       LF                       $4.60              $690.00

     4760.1              SOFFIT

     Install 1/4" BCX plywood soffit.

                                                                                                                                                                  110.00       SF                      $3.10              $341.00

     Trade:     19         Paint & Wallpaper

 

     5656.1              PREP & PAINT EXTERIOR WOOD

     Cover ground with drop cloth. Scrape all loose, cracked, peeling and blistered paint. Remove all deteriorated glazing compound. Feather edges and dull gloss with sandpaper. Dispose of chips properly.  Mask or remove exterior fixtures.  Clean all surfaces to paint manufacturer's requirements.  Caulk and fill holes. Reglaze sash where compound is missing.  Spot prime and top coat with two coats of two colors with owner's choice of premixed acrylic latex.  If an airless sprayer is used, the first coat must be brushed or rolled into the surface to promote good adhesion.  Where gutters and downspouts are to remain, painting of these should be included.  Removal and replacement of storm windows should be included.  Painting of wood shutters should be included.

                                                                                                                                                                      1.00       DU              $4,500.00          $4,500.00

 

                                                                                                                                                Totals for Location:  2  Exterior:       $37,844.50

     Location:  3  Basement

 

     Spec                                                                                                                                                                                                Unit                  Total

     Number       Spec                                                                                                                         Quantity        Units        Price                  Price

 

     Trade:     7           Masonry

 

     1105.1              FOUNDATON--PARGET

     Parget foundation wall with 3/8" coat of waterproof cement.  Match existing finish as closely as possible.

                           INTERIOR OF STONE WALLS.

                                                                                                                                                                  420.00       SF                      $1.10              $462.00

     Trade:     21         HVAC

 

     6050.1              FURNACE & DUCT--GAS: 80,000 BTU

     Install an 80,000 BTU, intermit. pilot, forced air furnace, minimum  AFUE rating of 80; complete with plenum, insulated

    supply duct, galvanized return duct connected to wall registers, to service all rooms.  Include setback thermostat, filter,

    fan and plenum control. (Connect thimble breaching to chimney per code. Provide separate power circuit per code.  "As

    needed")  Provide operating manual to owner.

                                                                                                                                                                      1.00       EA              $4,210.00          $4,210.00

     6410.1              FLUE REPLACE

     Install a prefabricated, double walled, UL listed, galvanized steel, 8" flue inside chimney.

                                                                                                                                                                    20.00       LF                     $45.00              $900.00

 

 

 

     Trade:     22         Plumbing

 

     6612.1              WATER SERVICE--COPPER K LINE

     Excavate to 36", lay 1" type K, copper pipe and refill trench for water service.  Lay line without joints from meter hub to main

    shut off valve inside structure.  Contractor to apply and pay for all permits, repair concrete cuts and coordinate installation

    of new meter. Owner to pay all water tap fees.  Backfill, seed and mulch disturbed yard areas.

                                                                                                                                                                    40.00       LF                     $52.00          $2,080.00

     6765.1              GAS LINE

     Hang 3/4" main and 1/2" fixture gas supply lines of schedule 40 black steel pipe with malleable iron screwed fittings.  Install

    brass stop valves at all equipment.

                                                                                                                                                                    60.00       LF                     $14.65              $879.00

     7070.1              WATER HEATER--40 GALLON GAS

     Install a 40 gallon, glass lined, high recovery, insulated to minimum R-7, gas water heater with a 6 year warranty.  Include

    pressure and temperature relief valve, discharge tube to within 6" of floor or to outside of structure, vent, thimble, and gas

    piping from shut-off valve to fixture.  Dispose of old water heater in code legal dump.

                                                                                                                                                                      1.00       EA                 $500.00              $500.00

     7190.1              WATER SUPPLY--1 BATH HOUSE

     Remove all water supply from meter on, to code legal dump. Install type M copper supply lines with 3/4" main, 1/2" fixture

    grouping trunk, and 3/8" individual supply lines to service one 3-piece bath, kitchen & laundry area. Installation shall be

    complete, code compliant, fully usable, and include shut-off valves, chromed fixture supply lines & air gaps.

                                                                                                                                                                      1.00       EA              $2,700.00          $2,700.00

     7210.1              DRAIN/WASTE/VENT--1 BATH HSE

     Remove all drain, waste and wet vent lines to code legal dump.  Install schedule 40 PVC or cast iron DWV lines to service

    one 3-piece bath, kitchen and laundry area from the foundation perimeter to roof vent terminus.

                                                                                                                                                                      1.00       DU              $2,100.00          $2,100.00

     Trade:     23         Electric

 

     7470.1              ELECTRIC SERVICE--150 AMP

     Dispose of old electric service to code legal dump.  Install a residential, 150 amp, single phase, 3 wire electric service.

    Include a main disconnect, 30 circuit panel board, meter socket, weather head, service cable, and ground rod and cable.

    Caulk exterior service penetration.

                                                                                                                                                                      1.00       EA              $1,250.00          $1,250.00

     8105.1              WIRING SYSTEM REPAIR

     Inspect, test and repair existing wiring system throughout the structure.  Install all necessary materials so that each existing

    outlet, fixture, motor, switch and circuit will operate properly and will conform to local electrical code. Verify that fixtures are

    securely mounted to wall or ceiling; which may require the installation of ceiling-fan rated boxes. Dispose of all defective and

    unnecessary wiring.  Fish all wire and patch all tear out.

                                                                                                                                                                      1.00       DU              $2,500.00          $2,500.00

 

                                                                                                                                          Totals for Location:  3  Basement:       $17,581.00

     Location:  4  Kitchen/dining

 

     Spec                                                                                                                                                                                                Unit                  Total

     Number       Spec                                                                                                                         Quantity        Units        Price                  Price

 

     Trade:     10         Carpentry

 

     2840.1              TRIM--WINDOW SET, INTERIOR

     Trim window including header, stops, casings, stool and apron in 2-1/2" wide finger jointed pine.

                                                                                                                                                                      2.00       EA                    $57.00              $114.00

     3310.1              TRIM--DOOR SET FINGER JOINTED

     Trim both sides of interior door, including header, stops, and casings.  Use 2-1/2" wide clamshell, finger jointed pine.

                                                                                                                                                                      1.00       EA                    $60.00                $60.00

     3345.1              DOOR--FLUSH INT, HOLLOW CORE

     Install flush, hollow core door on existing jamb to match.  Include privacy lockset and hinges.

                                                                                                                                                                      1.00       EA                 $112.00              $112.00

     3715.1              CABINET--WOOD BASE

     Dispose of base cabinets.  Install base cabinet with doors of solid birch or ash stiles and veneered plywood panels.  Frame

    with solid birch or ash stiles, 1/4" veneered plywood sides and metal or plastic corner bracing.  Drawers shall be made of

    wood or composition material.  Owner's choice of two in-stock designs.

                                                                                                                                                                    12.00       LF                  $106.00          $1,272.00

     3725.1              CABINET--WOOD WALL

     Dispose of wall cabinets.  Field measure and screw to studs, level and plumb, kitchen wall cabinet.  Door to have solid wood

    stiles and plywood panels.  Frame to have solid wood stiles, 1/4" plywood sides, metal or plastic corner bracing.

                                                                                                                                                                    12.00       LF                     $70.00              $840.00

     3750.1              COUNTER TOP--PLASTIC LAMINATE

     Dispose of counter top.  Field measure and screw to base cabinet a post formed, plastic laminate counter top.  Provide cutout

    for sink.  Owner's choice of in-stock color and texture.

                                                                                                                                                                    12.00       LF                     $35.00              $420.00

     Trade:     17         Drywall & Plaster

 

     5265.1              DRYWALL--3/8"

     Hang, tape and 3 coat finish 3/8" drywall. Glue each framing member and screw or nail 8" on center.  Run boards with long

    dimension horizontal.  Sand ready for paint.

                                                                                                                                                              1,204.00       SF                      $1.00          $1,204.00

     Trade:     19         Paint & Wallpaper

 

     5555.1              PREP/PAINT KITCHEN--SEMI GLOSS

     Remove/cover all hardware, fixtures not to be painted.  Wet scrape loose, cracked, peeling, blistered surfaces.  Feather edges

    & dull gloss surfaces w/sandpaper.  Clean all surfaces with TSP.  Fill all holes/cracks. Spot prime with acrylic latex.  Apply

    top coat of owner's choice of premixed acrylic latex semi-gloss.  Include any closets.

                                                                                                                                                                      1.00       RM                 $500.00              $500.00

     Trade:     20         Floor Coverings

 

     5930.1              UNDERLAY & VINYL SHEET GOODS

     Install 5/16" underlayment grade plywood, using 7d screw shank or cement coated nails, 6" on center allowing a 1/4" gap at

    wall. Install 070" thick, backed vinyl sheet goods w/ minimum seams, per manufact. recommendations. Caulk edges of vinyl

    w/clear silicone caulk to create positive seal.  Install metal edge strips in openings & shoe molding or 4" vinyl base around

    perimeter.

                                                                                                                                                                  350.00       SF                      $6.00          $2,100.00

     Trade:     22         Plumbing

 

     6835.1              SINK--DOUBLE BOWL COMPLETE

     Install a 33"x22"x5" double bowl, stainless steel, self rimming kitchen sink including a single control, metal bodied faucet

    with a "limited lifetime function and finish warranty" American Standard or equal and maximum flow of 2 gallons per minute,

    trap, supply lines, and shut-off valves.

                                                                                                                                                                      1.00       EA                 $500.00              $500.00

     Trade:     23         Electric

 

     7730.1              LIGHT FIXTURE--REPLACE

     Replace a ceiling mounted, 2 bulb, UL approved, incandescent light fixture with shade and lamps.  $20 allowance for fixture.

                                                                                                                                                                      2.00       EA                    $40.00                $80.00

 

                                                                                                                                 Totals for Location:  4  Kitchen/dining:          $7,202.00

     Location:  5  Bathroom

 

     Spec                                                                                                                                                                                                Unit                  Total

     Number       Spec                                                                                                                         Quantity        Units        Price                  Price

 

     Trade:     10         Carpentry

 

     2840.1              TRIM--WINDOW SET, INTERIOR

     Trim window including header, stops, casings, stool and apron in 2-1/2" wide finger jointed pine.

                                                                                                                                                                      1.00       EA                    $57.00                $57.00

     3360.1              DOOR--PREHUNG PASSAGE

     Install a 1-3/8" prehung, flush, luaun door and split jamb including casing both sides, 2 butt hinges and a privacy lockset.

                                                                                                                                                                      1.00       EA                 $160.00              $160.00

     3680.1              TUB SURROUND--PREFAB

     Install a white fiberglass or acrylic, 3- or 5-piece, tub surround kit with a built-in soap dish.  Caulk all joints with white,

    mildew resistant siliconized caulk.  Prepare substrate and attach panels using manufacturer's recommended adhesive and

    fasteners.

                                                                                                                                                                      1.00       EA                 $265.00              $265.00

     3835.1              ACCESSORY SET--6 PIECE CHROME

     Install a chrome plated steel bathroom accessory set consisting of two 24" towel bars, soap dish, tumbler holder, soap and

    grab, and toilet paper holder.  $55 allowance per set.

                                                                                                                                                                      1.00       EA                 $115.00              $115.00

     3840.1              SHOWER CURTAIN ROD

     Dispose of shower curtain rod.  Fill all holes or irregularities, flush with surrounding finish.  Install a chrome shower curtain

    rod using wall anchors.

                                                                                                                                                                      1.00       EA                    $25.00                $25.00

     Trade:     17         Drywall & Plaster

 

     5265.1              DRYWALL--3/8"

     Hang, tape and 3 coat finish 3/8" drywall. Glue each framing member and screw or nail 8" on center.  Run boards with long

    dimension horizontal.  Sand ready for paint.

                                                                                                                                                                  320.00       SF                      $1.00              $320.00

     Trade:     19         Paint & Wallpaper

 

     5560.1              PREP & PAINT BATHROOM

     Remove/cover all hardware and fixtures not to be painted.  Wet scrape all loose cracked, peeling blistered surfaces.  Clean

    surfaces with TSP.  Fill all holes and cracks. Spot prime with acrylic latex.  Apply top coat of owner's choice of premixed

    acrylic latex semi-gloss.

                                                                                                                                                                      1.00       RM                 $200.00              $200.00

     Trade:     20         Floor Coverings

 

     5930.1              UNDERLAY & VINYL SHEET GOODS

     Install 5/16" underlayment grade plywood, using 7d screw shank or cement coated nails, 6" on center allowing a 1/4" gap at

    wall. Install 070" thick, backed vinyl sheet goods w/ minimum seams, per manufact. recommendations. Caulk edges of vinyl

    w/clear silicone caulk to create positive seal.  Install metal edge strips in openings & shoe molding or 4" vinyl base around

    perimeter.

                                                                                                                                                                    70.00       SF                      $6.00              $420.00

     Trade:     22         Plumbing

 

     6900.1              VANITY--24" COMPLETE

     Install a 24" vanity complete with plywood cabinet, cultured marble top, dual control, brass bodied, single lever faucet, supply

    risers, shut-off valves and all required waste connectors to complete the installation.

                                                                                                                                                                      1.00       EA                 $565.00              $565.00

     6945.1              BATHTUB--5' STEEL COMPLETE

     Install a 5' white, enameled, formed steel, tub complete with lever operated pop up drain and overflow, PVC waste, single

    lever, metal faucet, shower diverter and Delta 6122 water saving shower head.

                                                                                                                                                                      1.00       EA                 $835.00              $835.00

     7010.1              COMMODE--REPLACE

     Install 2 piece, close coupled, white, vitreous china, water saving commode made by American Standard, or equal. Include

    plastic or pressed wood white seat, supply pipe, shut-off valve, flap valve and wax seal.  Allow for floor flange

    replacement if necessary.  Use 14" rough-in when replacing wall hung commode, and 12" rough-in to replace close

    coupled commode.

                                                                                                                                                                      1.00       EA                 $275.00              $275.00

     Trade:     23         Electric

 

     7816.1              FIXTURE--HEAT, LIGHT, VENT

     Install a ceiling mounted fixture containing a 1200 watt, forced air heater, a single bulb light fixture, and an exterior

    ducted vent fan with damper capable of 60 cfm, controlled by 3 manufacturer-supplied switches on an independent 20 amp

    circuit, using #14 copper Romex.  Fish all wireand patch all tear out.

                                                                                                                                                                      1.00       EA                 $325.00              $325.00

 

                                                                                                                                           Totals for Location:  5  Bathroom:          $3,562.00

 


 

     Location:  6  Living Room

 

     Spec                                                                                                                                                                                                Unit                  Total

     Number       Spec                                                                                                                         Quantity        Units        Price                  Price

 

     Trade:     10         Carpentry

 

     2840.1              TRIM--WINDOW SET, INTERIOR

     Trim window including header, stops, casings, stool and apron in 2-1/2" wide finger jointed pine.

                                                                                                                                                                      4.00       EA                    $57.00              $228.00

     3310.1              TRIM--DOOR SET FINGER JOINTED

     Trim both sides of interior door, including header, stops, and casings.  Use 2-1/2" wide clamshell, finger jointed pine.

                                                                                                                                                                      1.00       EA                    $60.00                $60.00

     3360.1              DOOR--PREHUNG PASSAGE

     Install a 1-3/8" prehung, flush, luaun door and split jamb including casing both sides, 2 butt hinges and a privacy lockset.

                                                                                                                                                                      1.00       EA                 $160.00              $160.00

     Trade:     17         Drywall & Plaster

 

     5265.1              DRYWALL--3/8"

     Hang, tape and 3 coat finish 3/8" drywall. Glue each framing member and screw or nail 8" on center.  Run boards with long

    dimension horizontal.  Sand ready for paint.

                                                                                                                                                                  860.00       SF                      $1.00              $860.00

     Trade:     19         Paint & Wallpaper

 

     5565.1              PREP & PAINT VACANT ROOM

     Remove/cover all hardware, fixtures not to be painted.  Wet scrape loose, cracked, peeling, blistered surfaces.  Feather edges

    & dull gloss surfaces with sandpaper.  Clean all surfaces with TSP.  Spot prime and top coat trim, ceiling, walls, doors &

    windows with owner's choice of premixed acrylic latex.  Include any closets.

                                                                                                                                                                      1.00       RM                 $300.00              $300.00

     Trade:     20         Floor Coverings

 

     5970.1              CARPET AND PAD

     Install FHA approved, nylon, plush carpet over a 1/2" medium density rebond pad w/ a minimum of seams. Stretch carpet to

    eliminate puckers, scallops & ripples. Include tackless strips, metal edge strips, and mending tape to cover entire floor

    including closets.  On stairs, fasten carpet and pad at top and bottom of each riser.  Owner's choice of stock color and

    pattern.

                                                                                                                                                                    35.00       SY                    $26.00              $910.00

     Trade:     23         Electric

 

     7730.1              LIGHT FIXTURE--REPLACE

     Replace a ceiling mounted, 2 bulb, UL approved, incandescent light fixture with shade and lamps.  $20 allowance for fixture.

                                                                                                                                                                      2.00       EA                    $40.00                $80.00

 

                                                                                                                                     Totals for Location:  6  Living Room:          $2,598.00

     Location:  7  Rear Porch

 

     Spec                                                                                                                                                                                                Unit                  Total

     Number       Spec                                                                                                                         Quantity        Units        Price                  Price

 

     Trade:     10         Carpentry

 

     3560.1              PORCH--REBUILD

     Remove deteriorated porch.  Construct 12"x 12" masonry piers, 2"x 10" joists with 3/4" tongue and groove flooring to support

    child-proof wood railing and 4"x 4" posts for roof. Construct roof structure with 2"x 6" rafters, 1/2" plywood deck, fiberglass

    shingles, aluminum gutter and downspouts and 1/4" plywood ceiling.  Structural lumber and deck shall be preservative

    treated.

                                                                                                                                                                    72.00       SF                    $26.00          $1,872.00

 

 

     3590.1              STEPS/LANDING--REPL EXTERIOR

     Dispose of existing steps and landing. Construct a replacement unit with two 2"x 12" preservative treated pine stringers, 5/4"

    PTP stepping stock treads, on a solid concrete footer.  Frame stairs 3' wide connecting to a 5'x 6' landing, of 2"x 6"s and

    2"x 4" deck. Construct a wood handrail on one side 32" above tread nosing.

                                                                                                                                                                      1.00       EA                 $480.00              $480.00

 

                                                                                                                                       Totals for Location:  7  Rear Porch:          $2,352.00

     Location:  8  Utility Room

 

     Spec                                                                                                                                                                                                Unit                  Total

     Number       Spec                                                                                                                         Quantity        Units        Price                  Price

 

     Trade:     10         Carpentry

 

     2840.1              TRIM--WINDOW SET, INTERIOR

     Trim window including header, stops, casings, stool and apron in 2-1/2" wide finger jointed pine.

                                                                                                                                                                      2.00       EA                    $57.00              $114.00

     3310.1              TRIM--DOOR SET FINGER JOINTED

     Trim both sides of interior door, including header, stops, and casings.  Use 2-1/2" wide clamshell, finger jointed pine.

                                                                                                                                                                      1.00       EA                    $60.00                $60.00

     Trade:     17         Drywall & Plaster

 

     5265.1              DRYWALL--3/8"

     Hang, tape and 3 coat finish 3/8" drywall. Glue each framing member and screw or nail 8" on center.  Run boards with long

    dimension horizontal.  Sand ready for paint.

                                                                                                                                                                  388.00       SF                      $1.00              $388.00

     Trade:     19         Paint & Wallpaper

 

     5565.1              PREP & PAINT VACANT ROOM

     Remove/cover all hardware, fixtures not to be painted.  Wet scrape loose, cracked, peeling, blistered surfaces.  Feather edges

    & dull gloss surfaces with sandpaper.  Clean all surfaces with TSP.  Spot prime and top coat trim, ceiling, walls, doors &

    windows with owner's choice of premixed acrylic latex.  Include any closets.

                                                                                                                                                                      1.00       RM                 $300.00              $300.00

     Trade:     20         Floor Coverings

 

     5930.1              UNDERLAY & VINYL SHEET GOODS

     Install 5/16" underlayment grade plywood, using 7d screw shank or cement coated nails, 6" on center allowing a 1/4" gap at

    wall. Install 070" thick, backed vinyl sheet goods w/ minimum seams, per manufact. recommendations. Caulk edges of vinyl

    w/clear silicone caulk to create positive seal.  Install metal edge strips in openings & shoe molding or 4" vinyl base around

    perimeter.

                                                                                                                                                                    96.00       SF                      $6.00              $576.00

     Trade:     23         Electric

 

     7730.1              LIGHT FIXTURE--REPLACE

     Replace a ceiling mounted, 2 bulb, UL approved, incandescent light fixture with shade and lamps.  $20 allowance for fixture.

                                                                                                                                                                      1.00       EA                    $40.00                $40.00

 

                                                                                                                                      Totals for Location:  8  Utility Room:          $1,478.00

     Location:  9  Bedroom

 

     Spec                                                                                                                                                                                                Unit                  Total

     Number       Spec                                                                                                                         Quantity        Units        Price                  Price

     Trade:     10         Carpentry

 

     2980.1              WINDOW--VINYL - DBL GLZ

     Field measure, order and install a like functioning vinyl, double glazed, replacement window and jamb including screen, caulk,

    interior casing and exterior trim.  If applicable, provide snap-in or internal grill to match mullion pattern of other openings.

                           Include framed opening.

                                                                                                                                                                      2.00       EA                 $750.00          $1,500.00

     3360.1              DOOR--PREHUNG PASSAGE

     Install a 1-3/8" prehung, flush, luaun door and split jamb including casing both sides, 2 butt hinges and a privacy lockset.

                                                                                                                                                                      1.00       EA                 $160.00              $160.00

     Trade:     17         Drywall & Plaster

 

     5265.1              DRYWALL--3/8"

     Hang, tape and 3 coat finish 3/8" drywall. Glue each framing member and screw or nail 8" on center.  Run boards with long

    dimension horizontal.  Sand ready for paint.

                                                                                                                                                                  420.00       SF                      $1.00              $420.00

     Trade:     19         Paint & Wallpaper

 

     5565.1              PREP & PAINT VACANT ROOM

     Remove/cover all hardware, fixtures not to be painted.  Wet scrape loose, cracked, peeling, blistered surfaces.  Feather edges

    & dull gloss surfaces with sandpaper.  Clean all surfaces with TSP.  Spot prime and top coat trim, ceiling, walls, doors &

    windows with owner's choice of premixed acrylic latex.  Include any closets.

                                                                                                                                                                      1.00       RM                 $300.00              $300.00

     Trade:     20         Floor Coverings

 

     5970.1              CARPET AND PAD

     Install FHA approved, nylon, plush carpet over a 1/2" medium density rebond pad w/ a minimum of seams. Stretch carpet to

    eliminate puckers, scallops & ripples. Include tackless strips, metal edge strips, and mending tape to cover entire floor

    including closets.  On stairs, fasten carpet and pad at top and bottom of each riser.  Owner's choice of stock color and

    pattern.

                                                                                                                                                                    12.00       SY                    $26.00              $312.00

     Trade:     23         Electric

 

     7730.1              LIGHT FIXTURE--REPLACE

     Replace a ceiling mounted, 2 bulb, UL approved, incandescent light fixture with shade and lamps.  $20 allowance for fixture.

                                                                                                                                                                      1.00       EA                    $40.00                $40.00

 

                                                                                                                                            Totals for Location:  9  Bedroom:          $2,732.00

     Location:  10  Attic

 

     Spec                                                                                                                                                                                                Unit                  Total

     Number       Spec                                                                                                                         Quantity        Units        Price                  Price

 

     Trade:     15         Roofing

 

     4425.1              RAFTER--2"X 8" REPLACE

     Dispose of existing defective rafter.  Install a 2"x 8" pine rafter, crown up, from ridge board to fascia.  Renail sheathing with

    coated sinkers to new rafter.

                                                                                                                                                                  600.00       LF                       $1.60              $960.00

     4450.1              FRAME ROOF--FLAT 2"X 8"

     Frame roof structure for flat roof using 2"x8" pine, 16" on center and 1/2" CDX sheathing.

                                                                                                                                                                  232.00       SF                      $4.10              $951.20

     Trade:     16         Conservation

 

     4905.1              INSULATE WALL--R-13 BATT

     Staple 3-1/2" thick, R-13, foil faced fiberglass roll insulation to studs per manufacturer's specifications.

                                                                                                                                                              1,100.00       SF                      $0.55              $605.00

     4935.1              ATTIC R-30 CELLULOSE

     Blow in borax treated, cellulose insulation per manufacturer's specifications to create an R-30 rating.  Cover any recessed

    ceiling light fixtures with an approved baffle.  Replace all material removed or cut to gain access to match existing materials.

                                                                                                                                                                  800.00       SF                      $1.25          $1,000.00

 

                                                                                                                                                    Totals for Location:  10  Attic:          $3,516.20

 

                                                                                   Total for project CRP032206 / 429 INDIANA Street / 1:       $80,365.70