Stoneridge Drive 12/6/2005
STREET, STORM SEWER IMPROVEMENTS
PROJECT NO.
RESOLUTION NO.
ESTIMATED COSTS:
Engineering (10%) $40,000.00
Construction
   Street, Storm Sewer $450,000.00
    Roundabout $0.00
    Waterline $0.00
Inspection/Administration (3%) $12,000.00
Legal & Issuance Costs (2%) $8,000.00
Interest on Temporary Notes (5%) $20,000.00
Subtotal $530,000.00
Property Acquisition $60,000.00
Relocation of utilities $0.00
Contigency $60,000.00
Grand Total $650,000.00
MAXIMUM ASSESSMENTS: $650,000.00
less additional width (City Share) $50,000.00
Total Assessed $600,000.00
East Side  50%  $                                      300,000.00
 West Side  50%  $                                      300,000.00
Plate No. Property Owner Lot Number Front Footage % Ass. Per Parcel ($)
  East Side
400345A MS Construction unplatted 624.00 50.0000%  $          300,000.00
West Side
U15801A Collister unplatted 624.00 50.0000%  $          300,000.00
 $          600,000.00