Memorandum

City of Lawrence

Utilities Department

 

TO:

Mike Wildgen

David Corliss

Debbie Van Saun

FROM:

Philip Ciesielski

CC:

Dave Wagner

Jim Stuit

Michael Tubbs

Date:

January 17, 2006

RE:

January 24, 2006 Agenda Item

 

Please include the following item on the City Commission consent agenda for consideration at the January 24, 2006 meeting:

Authorize the City Manager to enter into a contract with Professional Engineering Consultants, P.A. for design, bid and construction phase services for the Clinton Parkway & Kasold (Utilities Department Project Number CS05-01); the 22nd & Quail Creek (Utilities Department Project Number CS25-03) and the Alvamar Area (Utilities Department Project Number CS05-02) Sanitary Sewer Improvement Projects in the amount of $118,391.00.

 

The services are required for completion of the Clinton Parkway & Kasold, the 22nd & Quail Creek, and the Alvamar Area Sanitary Sewer Improvement Projects.  These improvements were presented as part of the 2003 Wastewater Master Plan.  The recommended projects consist of a combination of relief sewer construction, sewer replacement, manhole rehabilitation and pipe repairs along the alignment shown on the attached map.

 

Project History

 

February 2005 – Staff advertised a Request for Proposals for the above listed projects termed the Alvamar Area Sanitary Sewer Improvements.

March 2005 – Staff received nine Proposals from interested engineering consultants.  After an initial evaluation, four of the firms were invited to take part in interviews.

April 2005 – Staff conducted interviews with the selected engineering consultants.  Based on the results of these interviews, the City engaged Professional Engineering Consultants, P.A. and Wade & Associates for Study Phase Services for the Alvamar Area Sanitary Sewer Improvements at a cost of $40,648.00

August 2005 – Preliminary Report is received and reviewed by City Staff.

September 2005 – The Design Memorandum “Alvamar Area Sanitary Sewer Improvement Project”, based on the detailed study of the projects presented in the Preliminary Report, is received and reviewed by Staff.

Project Status.  The study and evaluation phase is concluded and the improvement locations and methods have been identified by the Consultant and reviewed by City Staff.

Project Details.  The project recommends the replacement/upsizing of 5,648 LF of existing sanitary sewer line; the rehabilitation of 18 existing manholes; and cleaning, CCTV inspection and selected point repairs along 4,940 LF of existing sanitary sewer line.  Various methods of pipe replacement will be evaluated during the design process to arrive at the best method for each pipe reach based topography, access, required increase in pipe diameter and impact on the surrounding community.

Proposed Project Schedule.

Project Design          January 2006 – May 2006

Review/Approval       May 2006 – June 2006

Advertise/Bid/Award   June 2006 – August 2006

Construction             August 2006 – May 2007          

Project Funding.  This project will be funded from the non-bonded construction fund. The estimated project cost, in 2005 dollars, provided in the 2003 Wastewater Master Plan for design and construction is $2,103,000.00.

 

Action Request.  Utility Department staff requests approval from the City Commission for the City Manager to enter into a Contract with Professional Engineering Consultants, P.A. in the amount of $118,391.00 for design, bid and construction phase services for the Alvamar Area Sanitary Sewer Improvement Project.