| Lawrence Municipal Airport | ||||||||||
| Lawrence, Kansas | ||||||||||
| AIP Project No. 3-20-0047-12 | ||||||||||
| July 19, 2005 | ||||||||||
| Bid Tabulation | ||||||||||
| Replace Medium Intensity Runway Lighting System for Runway 15-33 & | ||||||||||
| Medium Intensity Taxiway Lighting System for Taxiway "A" | ||||||||||
| Engineer's | Capitol Electric | DACO Construction | ||||||||
| Estimate | Construction Co., Inc. | Company, Inc. | ||||||||
| Item No. | Description | Quantity | Unit | Unit Cost | Est. Cost | Unit Cost | Est. Cost | Unit Cost | Est. Cost | |
| P-100 | Mobilization | 1 | L.S. | $11,600.00 | 11,600.00 | $9,019.95 | 9,019.95 | $9,761.00 | 9,761.00 | |
| L-108a | Cable, 1/C #8, 5kV, L-824C | 20,500 | L.F. | 1.50 | 30,750.00 | 1.20 | 24,600.00 | 1.25 | 25,625.00 | |
| L-108b | Cable, 1/C #6 Bare Copper Counterpoise | 16,000 | L.F. | 1.50 | 24,000.00 | 0.45 | 7,200.00 | 0.75 | 12,000.00 | |
| L-108c | Cable, 1/C #6, 600V, XHHW Green Ground | 16,000 | L.F. | 1.00 | 16,000.00 | 0.39 | 6,240.00 | 0.75 | 12,000.00 | |
| L-110a | 1-Way, 2-Inch PVC Duct (DEB) | 16,000 | L.F. | 4.50 | 72,000.00 | 1.77 | 28,320.00 | 4.50 | 72,000.00 | |
| L-110b | 2-Way, 2-Inch PVC Duct (CE) | 45 | L.F. | 50.00 | 2,250.00 | 46.25 | 2,081.25 | 35.00 | 1,575.00 | |
| L-110c | 2-Way, 2-Inch Duct (Directional Drill) | 215 | L.F. | 40.00 | 8,600.00 | 9.78 | 2,102.70 | * | 35.00 | 7,525.00 |
| L-110d | L-867 Size B Junction Box | 2 | Ea. | 400.00 | 800.00 | 515.89 | 1,031.78 | 525.00 | 1,050.00 | |
| L-125a | Remove Existing Edge Lights | 1 | L.S. | 5,000.00 | 5,000.00 | 6,717.66 | 6,717.66 | 1,500.00 | 1,500.00 | |
| L-125b | L-861 Elevated Runway Edge Light (Base Mount) | 42 | Ea. | 575.00 | 24,150.00 | 879.38 | 36,933.96 | 675.00 | 28,350.00 | |
| L-125c | L-861T Elevated Taxiway Edge Light (Base Mount) | 63 | Ea. | 575.00 | 36,225.00 | 869.61 | 54,785.43 | 650.00 | 40,950.00 | |
| L-126 | L-853 Retroreflective Taxiway Marker | 6 | Ea. | 100.00 | 600.00 | 104.61 | 627.66 | 110.00 | 660.00 | |
| Total | $231,975.00 | Total | $179,660.39 | * | Total | $212,996.00 | ||||
| L&S Electric. LLC | Huxtrable & Associates, Inc. | |||||||||
| Item No. | Description | Quantity | Unit | Unit Cost | Est. Cost | Unit Cost | Est. Cost | |||
| P-100 | Mobilization | 1 | L.S. | $11,500.00 | 11,500.00 | $5,000.00 | 5,000.00 | |||
| L-108a | Cable, 1/C #8, 5kV, L-824C | 20,500 | L.F. | 0.89 | 18,245.00 | 2.33 | 47,765.00 | * | ||
| L-108b | Cable, 1/C #6 Bare Copper Counterpoise | 16,000 | L.F. | 0.80 | 12,800.00 | 1.27 | 20,320.00 | * | ||
| L-108c | Cable, 1/C #6, 600V, XHHW Green Ground | 16,000 | L.F. | 0.82 | 13,120.00 | 1.12 | 17,920.00 | * | ||
| L-110a | 1-Way, 2-Inch PVC Duct (DEB) | 16,000 | L.F. | 5.49 | 87,840.00 | 9.71 | 155,360.00 | * | ||
| L-110b | 2-Way, 2-Inch PVC Duct (CE) | 45 | L.F. | 68.89 | 3,100.05 | 18.00 | 810.00 | |||
| L-110c | 2-Way, 2-Inch Duct (Directional Drill) | 215 | L.F. | 39.07 | 8,400.05 | 44.51 | 9,569.65 | * | ||
| L-110d | L-867 Size B Junction Box | 2 | Ea. | 492.50 | 985.00 | 500.00 | 1,000.00 | |||
| L-125a | Remove Existing Edge Lights | 1 | L.S. | 6,231.00 | 6,231.00 | 9,453.34 | 9,453.34 | |||
| L-125b | L-861 Elevated Runway Edge Light (Base Mount) | 42 | Ea. | 599.00 | 25,158.00 | 641.58 | 26,946.36 | * | ||
| L-125c | L-861T Elevated Taxiway Edge Light (Base Mount) | 63 | Ea. | 599.00 | 37,737.00 | 609.88 | 38,422.44 | |||
| L-126 | L-853 Retroreflective Taxiway Marker | 6 | Ea. | 200.00 | 1,200.00 | 100.00 | 600.00 | |||
| Total | $226,316.10 | Total | $333,166.79 | * | ||||||
| * Indicates correction to the extended bid price | ||||||||||