| City of Lawrence | ||||||||||||||||||||||||
| Project No. 3-TC1-104(C) | ||||||||||||||||||||||||
| Harvard Road, Monterey Way to Wakarusa Drive | ||||||||||||||||||||||||
| BID TAB | ||||||||||||||||||||||||
| Engineer's Estimate: $345,060.00 | ||||||||||||||||||||||||
| Bid Date: March 8, 2005 | ||||||||||||||||||||||||
| Pavers, Inc. | Harvard/Moundridge (TC) | Harvard/Mulberry ® | Harvard/Goldfield ® | Goldfield/Eldridge (TC) | Grove/Justin Cushion | Wheatstate/Eldgridge cushion | Andover/Prescott Cushion | Goldfield/Prescott(TC) | Goldfield Speed Hump | |||||||||||||||
| ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT PRICE | AMOUNT | Quantity | AMOUNT | Quantity | AMOUNT | Quantity | AMOUNT | Quantity | AMOUNT | Quantity | AMOUNT | Quantity | AMOUNT | Quantity | AMOUNT | Quantity | AMOUNT | Quantity | AMOUNT | |
| 1 | Mobilization | L.S. | 1 | $ 33,432.70 | $ 33,432.70 | 0 | $ 3,008.94 | 0 | $ 11,032.79 | 0 | $ 10,364.14 | 0 | $ 5,349.23 | 0 | $ 501.49 | 0 | $ 501.49 | 0 | $ 501.49 | 0 | $ 1,337.31 | 0 | $ 835.82 | |
| 2 | Embankment | C.Y. | 134 | $ 20.40 | $ 2,733.60 | 0 | $ - | 73 | $ 1,489.20 | 46 | $ 938.40 | 15 | $ 306.00 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 3 | Excavation | C.Y. | 75 | $ 30.65 | $ 2,298.75 | 0 | $ - | 22 | $ 674.30 | 30 | $ 919.50 | 23 | $ 704.95 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 4 | Contractor Furnished Embankment | C.Y. | 59 | $ 28.20 | $ 1,663.80 | 0 | $ 149.74 | 0 | $ 549.05 | 0 | $ 515.78 | 0 | $ 266.21 | 0 | $ 24.96 | 0 | $ 24.96 | 0 | $ 24.96 | 0 | $ 66.55 | 0 | $ 41.60 | |
| 5 | Subgrade (AB-3) | S.Y. | 3,445 | $ 8.55 | $ 29,454.75 | 143 | $ 1,222.65 | 1185 | $ 10,131.75 | 1099 | $ 9,396.45 | 635 | $ 5,429.25 | 50 | $ 427.50 | 50 | $ 427.50 | 50 | $ 427.50 | 135 | $ 1,154.25 | 98 | $ 837.90 | |
| 6 | Removal of Existing Structures | L.S. | 1 | $ 25,115.00 | $ 25,115.00 | 0 | $ 1,456.67 | 0 | $ 7,961.46 | 0 | $ 7,936.34 | 0 | $ 4,822.08 | 0 | $ 376.73 | 0 | $ 376.73 | 0 | $ 376.73 | 0 | $ 1,054.83 | 0 | $ 778.57 | |
| 7 | 8" Concrete Pavement | S.Y. | 1,587 | $ 56.80 | $ 90,141.60 | 0 | $ - | 564 | $ 32,035.20 | 570 | $ 32,376.00 | 412 | $ 23,401.60 | 0 | $ - | 0 | $ - | 0 | $ - | 41 | $ 2,328.80 | 0 | $ - | |
| 8 | 8" Stamped Concrete Pavement | S.Y. | 595 | $ 92.00 | $ 54,740.00 | 72 | $ 6,624.00 | 207 | $ 19,044.00 | 194 | $ 17,848.00 | 61 | $ 5,612.00 | 0 | $ - | 0 | $ - | 0 | $ - | 61 | $ 5,612.00 | 0 | $ - | |
| 9 | 6" Concrete Driveway | S.Y. | 134 | $ 47.85 | $ 6,411.90 | 0 | $ - | 31 | $ 1,483.35 | 70 | $ 3,349.50 | 33 | $ 1,579.05 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 10 | Stamped Asphalt | S.Y. | 69 | $ 70.00 | $ 4,830.00 | 69 | $ 4,830.00 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 11 | 4" Sidewalk | L.F. | 613 | $ 19.60 | $ 12,014.80 | 92 | $ 1,803.20 | 261 | $ 5,115.60 | 260 | $ 5,096.00 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 12 | Combined Curb and Gutter (Type I) | L.F. | 1,279 | $ 14.95 | $ 19,121.05 | 114 | $ 1,704.30 | 547 | $ 8,177.65 | 316 | $ 4,724.20 | 153 | $ 2,287.35 | 28 | $ 418.60 | 28 | $ 418.60 | 28 | $ 418.60 | 0 | $ - | 65 | $ 971.75 | |
| 13 | Combined Curb and Gutter (Type I) (Dry) | L.F. | 140 | $ 15.40 | $ 2,156.00 | 0 | $ - | 56 | $ 862.40 | 12 | $ 184.80 | 72 | $ 1,108.80 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 14 | Curb (Special) | L.F. | 500 | $ 18.40 | $ 9,200.00 | 100 | $ 1,840.00 | 110 | $ 2,024.00 | 110 | $ 2,024.00 | 90 | $ 1,656.00 | 0 | $ - | 0 | $ - | 0 | $ - | 90 | $ 1,656.00 | 0 | $ - | |
| 15 | Curb (Protection Type I) | L.F. | 216 | $ 23.10 | $ 4,989.60 | 40 | $ 924.00 | 57 | $ 1,316.70 | 57 | $ 1,316.70 | 31 | $ 716.10 | 0 | $ - | 0 | $ - | 0 | $ - | 31 | $ 716.10 | 0 | $ - | |
| 16 | Curb (Protection Type II) | L.F. | 387 | $ 21.50 | $ 8,320.50 | 0 | $ - | 208 | $ 4,472.00 | 179 | $ 3,848.50 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 17 | Sidewalk Access Ramps | Each | 27 | $ 840.00 | $ 22,680.00 | 8 | $ 6,720.00 | 8 | $ 6,720.00 | 8 | $ 6,720.00 | 3 | $ 2,520.00 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 18 | Speed Cushion | Each | 3 | $ 3,320.00 | $ 9,960.00 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 1 | $ 3,320.00 | 1 | $ 3,320.00 | 1 | $ 3,320.00 | 0 | $ - | 0 | $ - | |
| 19 | Speed Hump | Each | 1 | $ 6,970.00 | $ 6,970.00 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 1 | $ 6,970.00 | |
| 20 | Seeding, Fertilizing and Mulching | S.Y. | 301 | $ 1.00 | $ 301.00 | 70 | $ 70.00 | 140 | $ 140.00 | 91 | $ 91.00 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 21 | 12" White Cold Plastic Pavement Marking | L.F. | 189 | $ 7.00 | $ 1,323.00 | 0 | $ - | 36 | $ 252.00 | 36 | $ 252.00 | 0 | $ - | 39 | $ 273.00 | 39 | $ 273.00 | 39 | $ 273.00 | 0 | $ - | 0 | $ - | |
| 22 | 6" White Thermoplastic Pavement Marking | L.F. | 632 | $ 2.50 | $ 1,580.00 | 214 | $ 535.00 | 211 | $ 527.50 | 207 | $ 517.50 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 23 | Signing | L.S. | 1 | $ 5,980.00 | $ 5,980.00 | 0 | $ 538.20 | 0 | $ 1,973.40 | 0 | $ 1,853.80 | 0 | $ 956.80 | 0 | $ 89.70 | 0 | $ 89.70 | 0 | $ 89.70 | 0 | $ 239.20 | 0 | $ 149.50 | |
| 24 | 3/4" Type "K" Copper Pipe | L.F. | 37 | $ 98.35 | $ 3,638.95 | 0 | $ - | 24 | $ 2,360.40 | 13 | $ 1,278.55 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 25 | 3/4" Valve Sleeve | Each | 2 | $ 260.00 | $ 520.00 | 0 | $ - | 1 | $ 260.00 | 1 | $ 260.00 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 26 | Quick Coupling Assembly | Each | 2 | $ 650.00 | $ 1,300.00 | 0 | $ - | 1 | $ 650.00 | 1 | $ 650.00 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 27 | Water Valve Adjustment | Each | 7 | $ 525.00 | $ 3,675.00 | 3 | $ 1,575.00 | 2 | $ 1,050.00 | 1 | $ 525.00 | 1 | $ 525.00 | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | 0 | $ - | |
| 28 | Traffic Control | L.S. | 1 | $ 18,500.00 | $ 18,500.00 | 0 | $ 1,665.00 | 0 | $ 6,105.00 | 0 | $ 5,735.00 | 0 | $ 2,960.00 | 0 | $ 277.50 | 0 | $ 277.50 | 0 | $ 277.50 | 0 | $ 740.00 | 0 | $ 462.50 | |
| 29 | Landscaping | L.S. | 1 | $ 4,000.00 | $ 4,000.00 | 0 | $ 360.00 | 0 | $ 1,320.00 | 0 | $ 1,240.00 | 0 | $ 640.00 | 0 | $ 60.00 | 0 | $ 60.00 | 0 | $ 60.00 | 0 | $ 160.00 | 0 | $ 100.00 | |
| 30 | Construction Staking | L.S. | 1 | $ 9,500.00 | $ 9,500.00 | 0 | $ 855.00 | 0 | $ 3,135.00 | 0 | $ 2,945.00 | 0 | $ 1,520.00 | 0 | $ 142.50 | 0 | $ 142.50 | 0 | $ 142.50 | 0 | $ 380.00 | 0 | $ 237.50 | |
| GRAND TOTAL | $ 396,552.000 | $ 35,881.71 | $ 130,862.76 | $ 122,906.16 | $ 62,360.42 | $ 5,911.98 | $ 5,911.98 | $ 5,911.98 | $ 15,445.04 | $ 11,385.13 | $ 396,577.14 | |||||||||||||