| City of Lawrence | |||||||||
| Project No. 3-TC1-104(C) | |||||||||
| Harvard Road, Monterey Way to Wakarusa Drive | |||||||||
| BID TAB | |||||||||
| Engineer's Estimate: $345,060.00 | |||||||||
| Bid Date: March 8, 2005 | |||||||||
| Pavers, Inc. | Kansas Heavy Constr., L.L.C. | ||||||||
| ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT | ||
| 1 | Mobilization | L.S. | 1 | $ 33,432.70 | $ 33,432.70 | $ 10,000.00 | $ 10,000.00 | ||
| 2 | Embankment | C.Y. | 134 | $ 20.40 | $ 2,733.60 | $ 35.00 | $ 4,690.00 | ||
| 3 | Excavation | C.Y. | 75 | $ 30.65 | $ 2,298.75 | $ 46.00 | $ 3,450.00 | ||
| 4 | Contractor Furnished Embankment | C.Y. | 59 | $ 28.20 | $ 1,663.80 | $ 40.00 | $ 2,360.00 | ||
| 5 | Subgrade (AB-3) | S.Y. | 3,445 | $ 8.55 | $ 29,454.75 | $ 7.00 | $ 24,115.00 | ||
| 6 | Removal of Existing Structures | L.S. | 1 | $ 25,115.00 | $ 25,115.00 | $ 42,500.00 | $ 42,500.00 | ||
| 7 | 8" Concrete Pavement | S.Y. | 1,587 | $ 56.80 | $ 90,141.60 | $ 55.00 | $ 87,285.00 | ||
| 8 | 8" Stamped Concrete Pavement | S.Y. | 595 | $ 92.00 | $ 54,740.00 | $ 90.00 | $ 53,550.00 | ||
| 9 | 6" Concrete Driveway | S.Y. | 134 | $ 47.85 | $ 6,411.90 | $ 45.00 | $ 6,030.00 | ||
| 10 | Stamped Asphalt | S.Y. | 69 | $ 70.00 | $ 4,830.00 | $ 190.00 | $ 13,110.00 | ||
| 11 | 4" Sidewalk | L.F. | 613 | $ 19.60 | $ 12,014.80 | $ 12.50 | $ 7,662.50 | ||
| 12 | Combined Curb and Gutter (Type I) | L.F. | 1,279 | $ 14.95 | $ 19,121.05 | $ 17.50 | $ 22,382.50 | ||
| 13 | Combined Curb and Gutter (Type I) (Dry) | L.F. | 140 | $ 15.40 | $ 2,156.00 | $ 18.00 | $ 2,520.00 | ||
| 14 | Curb (Special) | L.F. | 500 | $ 18.40 | $ 9,200.00 | $ 21.50 | $ 10,750.00 | ||
| 15 | Curb (Protection Type I) | L.F. | 216 | $ 23.10 | $ 4,989.60 | $ 21.50 | $ 4,644.00 | ||
| 16 | Curb (Protection Type II) | L.F. | 387 | $ 21.50 | $ 8,320.50 | $ 21.50 | $ 8,320.50 | ||
| 17 | Sidewalk Access Ramps | Each | 27 | $ 840.00 | $ 22,680.00 | $ 1,385.00 | $ 37,395.00 | ||
| 18 | Speed Cushion | Each | 3 | $ 3,320.00 | $ 9,960.00 | $ 6,550.00 | $ 19,650.00 | ||
| 19 | Speed Hump | Each | 1 | $ 6,970.00 | $ 6,970.00 | $ 12,450.00 | $ 12,450.00 | ||
| 20 | Seeding, Fertilizing and Mulching | S.Y. | 301 | $ 1.00 | $ 301.00 | $ 3.00 | $ 903.00 | ||
| 21 | 12" White Cold Plastic Pavement Marking | L.F. | 189 | $ 7.00 | $ 1,323.00 | $ 7.50 | $ 1,417.50 | ||
| 22 | 6" White Thermoplastic Pavement Marking | L.F. | 632 | $ 2.50 | $ 1,580.00 | $ 3.00 | $ 1,896.00 | ||
| 23 | Signing | L.S. | 1 | $ 5,980.00 | $ 5,980.00 | $ 6,200.00 | $ 6,200.00 | ||
| 24 | 3/4" Type "K" Copper Pipe | L.F. | 37 | $ 98.35 | $ 3,638.95 | $ 38.00 | $ 1,406.00 | ||
| 25 | 3/4" Valve Sleeve | Each | 2 | $ 260.00 | $ 520.00 | $ 350.00 | $ 700.00 | ||
| 26 | Quick Coupling Assembly | Each | 2 | $ 650.00 | $ 1,300.00 | $ 400.00 | $ 800.00 | ||
| 27 | Water Valve Adjustment | Each | 7 | $ 525.00 | $ 3,675.00 | $ 450.00 | $ 3,150.00 | ||
| 28 | Traffic Control | L.S. | 1 | $ 18,500.00 | $ 18,500.00 | $ 20,000.00 | $ 20,000.00 | ||
| 29 | Landscaping | L.S. | 1 | $ 4,000.00 | $ 4,000.00 | $ 3,500.00 | $ 3,500.00 | ||
| 30 | Construction Staking | L.S. | 1 | $ 9,500.00 | $ 9,500.00 | $ 4,000.00 | $ 4,000.00 | ||