Please include the following item on the City Commission consent agenda for consideration at the November 16, 2004 meeting:

Project Description.  This project would involve the construction of a roundabout at the intersection of 19th and Louisiana

Project Description/History.  The city hired Wilson & Company to conduct a traffic calming study for Louisiana Street between 19th and 31st.  This study was completed in 2000 and involved many meetings for all the neighborhoods along this corridor.  Eleven projects/recommendations were identified:

 

  1. Roundabout at Louisiana Street and church/park entrance.
  2. Roundabout at Louisiana Street and 27th Terrace/school entrance.
  3. Roundabout at Louisiana Street and 27th Street.
  4. Median treatment between 25th Street and Utah Street.
  5. Roundabout at Louisiana Street and shipping strip mall entrance/Checkers grocery store.
  6. Median treatment between 22nd Street and Greever Terrace.
  7. Median treatment between 21st Street and 20th Street.
  8. Median treatment between 20th Street and 19th Street.
  9. Roundabout at Louisiana Street and 19th Street.
  10. Roundabout at Louisiana Street and 17th Street.
  11. Addition of sidewalk between Parkhill Terrace and 18th Street.

 

To date the City has completed items 4, 6, 7, 8, and 11.

 

Project Status.  Letters will be mailed to local engineering consultants to solicit design proposals for this project. 

 

Project Details.  The intersection will be designed for a roundabout and associated geometric improvements to replace the existing traffic signal.  Neighborhood input will be requested.  Both Centennial and University Place Neighborhood Associations were notified of this agenda item,  as well as the school and Parks Department.

 

The Louisiana Street Traffic Calming Study can be accessed at http://www.lawrencepublicworks.org/pdf/louisana-traffic-study.tif.

 

Project Funding.  Resolution 6478 was previously adopted by the City Commission on July 22, 2003 funding a portion of 19th and Louisiana along with 6th and Lawrence Avenue.  6th and Lawrence Avenue has been completed and approximately $65,000 remains for 19th and Louisiana.  Also, Resolution No. 6571 is on this agenda to authorize issuing an additional $250,000 in bonds to fund these improvements.  This amount was allocated in the Capital Improvement Budget for traffic signal renovations.

 

Action Request.  Adopt Resolution No. 6571 authorizing the issuance of bonds in the amount of $250,000 to fund the construction of a roundabout and other necessary geometric improvements at 19th and Louisiana.

 