Approved by City Commission
|
|
4/6/04
|
Original
Project:
|
Harvard Road from Wakarusa to Monterey Way
|
|
Engineering
|
|
$
53,146.07
|
|
Estimated Construction Cost:
|
|
|
Roundabout
|
Harvard/Mulberry
|
$100,000.00
|
|
|
Harvard/Goldfield
|
100,000.00
|
|
|
|
|
|
Traffic Circle
|
Harvard/Moundridge
|
25,000.00
|
|
|
|
|
|
Speed Cushion between
|
Moundridge/Mulberry
|
15,000.00
|
|
|
Goldfield/Eldridge
|
15,000.00
|
|
|
Andover/Prescott
|
15,000.00
|
|
|
|
$270,000.00
|
|
|
|
|
$323,146.07
|
|
|
|
|
|
4/6/04
|
Add:
|
Traffic Circle at Goldfield/Eldridge
|
|
Engineering
|
$6,000.00
|
|
|
|
$25,000.00
|
|
|
|
|
$354,146.47
|
Resolution 6536 authorized $360,000.00
|
|
|
|
|
|
|
|
|
|
|
|
6/22/04
|
Add:
|
Speed Hump on Goldfield between
Eldridge/Prescott
|
|
Engineering
|
$-0-
|
|
|
|
$15,000.00
|
|
|
|
|
$369,146.07
|
|
|
|
|
|
|
|
|
|
|
Pending City Commission
Approval – 8/10/04
|
Add:
|
Traffic Circle at Goldfield/Prescott
|
|
|
Engineering
|
$-0-
|
|
Construction
|
$25,000.00
|
|
|
|
$394,146.07
|
|
|
|
|
|
|
|
|
|
|
|