Approved by City Commission

 

4/6/04

Original Project:

Harvard Road from Wakarusa to Monterey Way

 

Engineering

 

               $ 53,146.07

 

Estimated Construction Cost:

 

 

Roundabout

Harvard/Mulberry

$100,000.00

 

 

Harvard/Goldfield

  100,000.00

 

 

 

 

 

Traffic Circle

Harvard/Moundridge

    25,000.00

 

 

 

 

 

Speed Cushion between

Moundridge/Mulberry

    15,000.00

 

 

Goldfield/Eldridge

15,000.00

 

 

Andover/Prescott

15,000.00

 

 

 

$270,000.00

 

 

 

 

             $323,146.07

 

 

 

 

4/6/04

Add:

Traffic Circle at Goldfield/Eldridge

 

Engineering

$6,000.00

 

 

Construction

$25,000.00

 

 

 

 

                $354,146.47

Resolution 6536 authorized $360,000.00

 

 

 

 

 

6/22/04

Add:

Speed Hump on Goldfield between Eldridge/Prescott

 

Engineering

$-0-

 

 

Construction

$15,000.00

 

 

 

 

                $369,146.07

 

 

 

 

Pending City Commission Approval – 8/10/04

Add:

Traffic Circle at Goldfield/Prescott

 

 

Engineering

$-0-

 

Construction

$25,000.00

 

 

 

                $394,146.07