| HARVARD ROAD, George Williams Way east approximately 500 feet | |||||
| STREET, STORM SEWER, WATERLINE IMPROVEMENTS | |||||
| PROJECT NO. 45-CP10-903(BD) | |||||
| RESOLUTION NO. 6503 = $550,000 | |||||
| July 19, 2004 | |||||
| MAXIMUM ASSESSMENTS | |||||
| Engineering-street, storm sewer | $32,786.25 | Stultz provides 8.6% up front ($971.36 paid) | |||
| Engineering-waterline | $4,071.00 | Stultz provides 17.2% up front ($241.22 paid) | |||
| Engineering - reinforced concrete box (city) | $10,576.50 | ||||
| Construction-street, storm sewer (estimate) | $446,536.00 | Stultz provides 8.6% up front | |||
| Construction-waterline (estimate) | $47,420.00 | Stultz provides 17.2% up front | |||
| Construction - reinforced concrete box (estimate) (city) | $160,000.00 | ||||
| Inspection/Administration | $14,818.68 | ||||
| Legal & Issuance Costs | $16,348.90 | ||||
| Interest on Temporary Notes | $32,697.80 | ||||
| Subtotal | $765,255.13 | ||||
| Less: City Share - reinforced concrete box culvert | $170,576.50 | ||||
| TOTAL | $594,678.63 | ||||
| Plate No. | Property Owner | Lot Number | Square Footage | Assessment. Per Tract ($) | |
| Parcel 1 (34.45%): | $ 204,866.79 | ||||
| U15802 | Harvard LC | 976,315 | $ 149,816.20 | ||
| U15802A | Alvamar, Inc. | 20,089 | $ 3,082.67 | ||
| U15802B | Alvamar, Inc. | 273,429 | $ 41,957.87 | ||
| U15802C | Alvamar, Inc. | 65,233 | $ 10,010.05 | ||
| 1,335,066 | 204,866.79 | ||||
| Parcel 2 (65.55%): | $ 389,811.84 | ||||
| U15817-01 | City of Lawrence - north side | 98,801 | $ 58,293.03 | ||
| U15817-01 | City of Lawrence - south side | 561,892 | $ 331,518.81 | ||
| 660,693 | $ 389,811.84 | ||||
| $ 594,678.63 | |||||